1.0 OBJECTIVE
OF PROCEDURE
This work method
statement covers the fencing works for (your project name).
This item shall consist
of furnishing and erecting fencing and gates in accordance to the specifications
and the details shown on the drawings or as directed by the E.R.
This work method
statement provides information concerning method of application to ensure
compliance with technical specification.
2.0 DESCRIPTION
To describe the method on how the installation of
fence and gate are carried out with approval from E.R.
3.0 MATERIALS
a.
Chain
link fencing
·
PVC
coated galvanised chain link fence and accessories
·
Angle
post
·
Formwork
·
Concrete
mix G20
b.
High
tensile cable fencing
·
High
tensile cable fence and accessories
·
GI
post
·
Concrete
mix G20
c.
GI
railing
·
GI
pipe & GI post
·
Welding
equipment
·
Concrete
mix G20 & G30
4.0 WORK
METHODOLOGY
4.1 GENERAL
The fence shall be constructed in accordance with
the details on the plans and as specified herein using new materials, and all
work shall be performed in a workmanlike manner satisfactory to the Consultant
/ E.R.
Prior to the beginning of the work or upon the
request of the Consultant, the Contractor shall locate the position of the work
by establishing and marking the fence line. The finished fence shall be plumb,
taut, true to line and ground contour, and complete in every detail.
There are five (5) basic steps involved in
installing the fence and each of those steps has several different, equally
effective options. There are;
·
Deciding
how many wires need and then marking how high up and far apart they need to be
placed on the ends and corners.
·
Insulating
the wires from the end and corner posts.
·
Stretching
the wire.
·
Connecting
the wire.
·
Installing
the in-line strainers, tension spring and then tightening the wire.
For handrail, all workmanship shall be of first
class quality in every respect, the greatest accuracy being observed to ensure
that all parts will fit together properly on erection. Erection procedure shall
be in accordance with approved proposal (mock-up). During erection care shall
be taken to avoid any shock, dynamic or vibrationary loading of the members.
All holes shall be accurately marked off from templates or corresponding
plates, and drilled, except in plates or under, when they may be punched. Holes
should be cleaned or burrs or rough edges and counter-sunk where required. The
surface area must be cleaned before proceed the work.
4.2 CHAIN
LINK FENCES
4.2.1 Clearing Fence Lines
The site of the fence shall be sufficiently cleared
of obstructions, and surface irregularities shall be graded so that the fence
will confirm to the general contour of the ground. The fence line shall be
cleared on each side of the fence centreline. This clearing shall consist of
rocks or other obstructions that will interfere with proper construction of
fence.
4.2.2 Installing Posts
The contractor shall fill, cut or trench where
necessary to produce a smooth and uniform ground surface so the bottom of the
fabrics not less than 300mm or more than 900mm above the finished ground line.
All posts shall be set plumb, true to line and grade. Terminal posts, defined
as end, corner, pull or gate posts, shall be set in concrete. The concrete
footing shall be uniform thickness around the post. Distance of post shall
according to the construction drawing and/or approved mock-up.
4.2.3 Bracing
All corner, end, pull, and gate posts shall be
braced as shown on the drawings. Pull posts shall be used at sharp breaks in
vertical grade or as directed by the Consultant.
4.2.4 Installing Fabric
Fabric shall be securely attached to end, corner,
gate and pull posts in accordance with manufacturer’s recommendations. All
fabrics shall be taut before attaching to line posts or tension wire. High and
size for the fabric should follow as per construction drawing.
(a) Weaving Chain Link Fabric
(b) Stretching Chain Link Fabric
i.
After
rolling out the chain link and weaving the rolls together, ‘hook-up’ one end.
Make sure the nuts are on the inside of the fence so they cannot be removed
from outside the enclosure.
ii.
Pull
the chain link tight by hand to the other end.
iii.
Stretch
the fence using stretch tools. Do not over tighten.
iv.
‘Dress’
the fabric as tighten it. ‘Dressing’ involves straightening the fabric diamonds
so they run true.
v.
Hand
stretch the small section of chain link left between the come-a-long and
terminal post by hand. Slide the tension bar into the mesh and make the last
hook-up. Once all bolts are in place, remove the stretching tools.
4.2.5 Fencing Kerb
The contractor shall erect the formwork after the
installation of chain link pole and the fabric. The height of kerb shall be 150mm.
The concreting work shall be carried out after the formwork erected with G20
concrete.
4.3 HIGH
TENSILE CABLE FENCES
High-tensile cable fence is an effective barrier
for controlling and protective livestock. Some advantages of this type of fence
include ease of handling, minimal maintenance and high strength. High-tensile
cable fence can be easily electrified and will outlast most other fences.
4.3.1 Clearing Fence Lines
The site of the fence shall be sufficiently cleared
of obstructions, and surface irregularities shall be graded so that the fence
will confirm to the general contour of the ground. The fence line shall be
cleared on each side of the fence centreline. This clearing shall consist of
rocks or other obstructions that will interfere with proper construction of
fence.
4.3.2 Installing Posts
The contractor shall fill, cut or trench where
necessary to produce a smooth and uniform ground surface. All posts shall be
set plumb, true to line and grade. Terminal posts, defined as end, corner, pull
or gate posts, shall be set in concrete grade 20. The concrete footing shall be
uniform thickness around the post, footing size 200x200x500mm. Distance of post
shall according to the construction drawing and/or approved mock-up, 3m
distance from post to other post.
4.3.3 Bracing
All corner, end, pull, and gate posts shall be
braced as shown on the drawings. Pull posts shall be used at sharp breaks in
vertical grade or as directed by the Consultant.
4.3.4 Installing Cable
High-tensile cable fencing is no more difficult to
erect than other kinds of fencing.
(a)
Insulating
the cable from the ends and corner posts.
Once the 12mm diameter high-tensile cable placements
on the end and corner post have been set, insulate the cable from the posts.
Next, fasten the ends of the wire together.
(b)
Stretching
and fastening the cable.
Compared to
other types of fences, this is probably one of the easiest parts of the whole
process. The cable must be stretching and fastening using cable tension.
(c)
Installing
the in-line strainers, tension spring and then tightening the cable.
The final step
in the process is tightening the cable. Once the fence cable has been hooked to
the ends it run the inline strainers can be installed.
4.4 GI
RAILING
4.4.1 Clearing GI Railing Lines
The site of the GI railing shall be sufficiently
cleared of obstructions, and surface irregularities shall be graded so that the
railing will confirm to the general contour of the ground. The railing line
shall be cleared on each side of the railing centreline. This clearing shall consist
of rocks or other obstructions that will interfere with proper construction of railing.
4.4.2 Installing Posts
The contractor shall fill, cut or trench where
necessary to produce a smooth and uniform ground surface. All posts shall be
set plumb, true to line and grade. Terminal posts, defined as end, corner, pull
or gate posts, shall be set in concrete grade 20 (for external GI railing) and using
bolt and nut (for internal GI railing), then cover with concrete grade 30 (for internal
GI railing). Distance of post shall according to the construction drawing
and/or approved mock-up.
4.4.3 Bracing
All corner, end, pull, and gate posts shall be
braced as shown on the drawings. Pull posts shall be used at sharp breaks in
vertical grade or as directed by the Consultant.
4.4.4 Installing Balustrade/Railing
It is easy and the best way when the balustrades
welding together with the post before install it at site. The welding spot must
be smooth finishes. After installation, there should be applied the last layer
of anti-corrosion coating, with approved colour code by consultant.
4.5 INSTALLING
GATES
The gates shall be erected and hung on gate
fittings as shown on the plans. They shall be attached in such a manner that
the gate cannot be lifted off the hinges. Gates shall be erected to swing in
the direction indicated and shall be provided with gate stops, as specified or
as shown on the drawings.
5.0 SAFETY
& ENVIRONMENTAL PROGRAMME
5.1 Safety
- All workers shall provide with PPE (Personal
Protective Equipment) and shall be worn every time they are entering the
site.
- Safety induction to be conducted to all new
workers that involved to this activity and safety tool box meeting shall
be conducted every day to remind the workers about concerning the safety.
- Safety Manager / Safety Supervisor shall
ensure that the activity shall carry out in a safe manager.
- All workers shall fully support and actively
participate in all safety related activities and comply with all
practicable safety measures.
- All workers shall be advised to report any
accident or injury to supervisor and proper treatment to be obtained.
- Rubber glove, mask and safety glasses should always be worn during
welding works in progress.
- The site shall be kept clear of unnecessary obstruction.
- First aid kit boxes will be provided at site office.
5.2 Environmental
- All workers shall educate on good environmental
management practices and well-disciplined to environment.
- The garbage bin shall be provided at the
working area and Supervisor shall ensure its must be collected regularly
and disposed-off at the approved dumpsite.
- Safety team shall ensure that no open burning
of construction or domestic wastes is practiced.
- All workers shall ensure that all tools and
equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.

This is a very good DIY tutorial for fence installation and explains every thing related to different types of fencing. I live in Leesburg VA and recently hired a fence installation service provider from nearby. I will show them this article for some useful tips.
ReplyDeletehttp://www.qrgdirect.com/All-American-Fences-installation-Leesburg-VA
thank you so much. I'm appreciate it...=)
DeleteThanks Ika. Fascinating and helpful!
ReplyDeleteExcellent! Thanks for the share!
ReplyDeleteTHIS IS LOVELY PLZ CAN I GET A WORK METHOD STATEMENT FOR SEPTIC TANK/SOAK AWAY CONSTRUCTION?
ReplyDeleteOz West Fencing specialise in Pool Fencing, CNC & Automatic Gates, Balustrade, Colorbond & Security. Perth Fencing Services
ReplyDeletefencing
Make sure iptables and selinux should be disabled on all machines. if you can set some iptables rules in that case you need to put below command's on host machines to accept the fence request. Fence Constriction
ReplyDeleteThis work method statement provides information concerning method of application to ensure compliance with technical specification.
ReplyDeletelocal fencing
ment providesfence cost
ReplyDeleteI have done my part, You can also do your part by commenting below the challenges you encountered while doing this.
ReplyDeleterail fence
very good info...thanks for sharing
ReplyDeleteI think chain link fencing is the best way of providing protection and security to backyards,playgrounds and swimming pools.Its durable and strong enough anyhow.
ReplyDeleteChain Link Fence
Thanks for providing this valuable information about
ReplyDeleteautomatic doors & gates But if you are looking for automatic doors & gates in UAE. Visit us at yellowpages.ae
Thanks for providing this valuable information about
ReplyDeleteautomatic doors & gates But if you are looking for automatic doors & gates in UAE. Visit us at yellowpages.ae
"Your Article is Good
ReplyDeleteFencing Work"
Thanks for sharing...Best Fencing Contractors in Chennai
ReplyDeleteI’m satisfied with just sharing this useful information with us. Please keep it up to date like this. Thank you for sharing.
ReplyDeleteSOD Installation Atlanta
Great Vinyl Fence Post Leveling Collars Ottawa! Easy to install and leveled my fence posts perfectly. Highly recommended!
ReplyDeleteThanks for sharing such an informative blog. Lighthouse Contractors excels in Fence installations near me. Professionalism and precision define their work, making them the preferred choice for all fencing needs.
ReplyDeleteInteresting
ReplyDeleteGreat breakdown of the installation process! A clear method statement always helps avoid confusion on-site, especially when dealing with measurements, alignment, and footing depth. Proper planning really does make the whole fencing and gate installation smoother. Anyone working with modern materials like a colorbond fence perth setup will definitely benefit from following a structured approach like this. Thanks for sharing such practical insights!
ReplyDeleteThe fencing and gate installation method statement outlines the complete procedure for constructing chain link fences, high-tensile cable fences, GI railings, and gates in compliance with project specifications and consultant requirements. It covers material selection, site clearing, post installation, bracing, wire stretching, concrete works, welding procedures, and gate mounting techniques. The document also emphasizes strict safety practices, PPE usage, environmental protection, and quality workmanship standards essential for professional commercial fence installation projects.
ReplyDeleteThank you for sharing this detailed method statement for the installation of fencing and gates. The step-by-step information is useful for understanding proper preparation, installation, and safety practices. Anyone planning a fencing project can also consider experienced Fencing Contractors In Perth to ensure the work is completed professionally and safely
ReplyDelete