jika kau fikirkan kau boleh! kau hampir boleh melakukan.. jika kau fikirkan ragu-ragu, usahamu tak menentu.. jika kau fikirkan kemenangan, kau menghampiri kejayaan.. jika kau fikirkan kekalahan, kau hampiri kegagalan.. renung-renungkan ~

Wednesday, February 26, 2014

Hijau itu Kedamaian~~


 Muadzam Shah Cattle Research and Innovation Centre, Pahang Darul Makmur~~

Method Statement -Water Proofing

1.0  OBJECTIVE OF PROCEDURE

This work method statement covers the applying waterproofing for (your project's name).

This work method statement provides information concerning method of application to ensure compliance with contract requirements and drawings besides to perform safe working environment and compliance with safety requirements.


2.0  DESCRIPTION

Estokote Grey is a cement based two component polymer modified flexible waterproof coating. When used in reservoir or similar structure, it is able to accommodate the bending moment of the structure when it is filled with water. It fills and seals pores and voids of concrete or Masonry Surfaces to prevent water infiltration.

It is compatible to concrete. The bonding agent imparts excellent adhesion to concrete surfaces and forms part of the structure.

Packing                  : 22.5 kg pack
Coverage               : 11 m² per pack per two coats


3.0  EQUIPMENT

·         Brush / Roller
·         Sponge
·         Glove
·         Spray


4.0  WORK METHODOLOGY

v  Preparation

a.       The surfaces, which are to receive Estokote Grey coating, must be free from oil, grease, wax, dirt or loosely adhering particles and sharp edges or any other form of foreign material, which might affect adhesion. The surface must be roughened.
b.       Spalled and deeply disintegrated concrete should be removed to sound concrete and repaired with a suitable concrete repair mortar.
c.        Absorbent surfaces have to be thoroughly saturated with water prior to application of first coat of Estokote Grey. However, no loose standing water should be on the surface before application.

v  Mixing

a.       Mix in a clean container by slowly adding the powder component to the liquid component.
b.       Stirring with slow speed mixer for 2 – 4 minutes to avoid lump formation.
c.        Use mixture within 30 minutes.
d.       Do not add water.


v  Application

a.       Whilst the substrate is still damp from saturation, apply the first coat.
b.       Leave to harden for approximately 4 – 8 hours at temperatures above 20°C before applying the second coat.
c.        Re-mixed the Estokote Grey material remained in mixing vessel for every application of Estokote Grey.
d.       For floor application, to avoid risk of damage to the first coat, it is recommended that the second coat be applied before 24 hours.
e.       If the second coat is applied 12 hours or later, the first coat shall be slightly pre-wetted, preferably using a fine spray.
f.         After the second coat has been applied, better finishing can be achieved by rubbing down with a soft, dry sponge.
g.        Floor screeding inside the water trough to be done before waterproofing applied.

v  Over Coating

a.       Allow the coating as above to be hardened for at least 3 days prior subsequence over coating work.

v  Protection

a.       The freshly applied waterproof coating shall be protected from rain, dirt, oil grease or other loose materials during its drying time.
b.       The contractor should also take precautions to protect the Estokote Grey coating from any mechanical damage during the construction of other trade of works.

v  Curing

a.       Precaution should be taken for applications done directly under sunlight and windy conditions. It should also be protected from direct rain for at least 4 hours.
b.       The finishing coat shall be cured for 3 – 5 days before other trade shall be proceeded.

v  Ponding Test

a.       The waterproof area has allowed to be cured for hours before ponding test was carried out for 24 hours duration.
b.       If the ponding test was failed, rectification work shall be carried out and after the rectification work was done, the ponding test will be carried out.


5.0  SAFETY & ENVIRONMENTAL PROGRAMME

5.1  Safety

  • All workers shall provide with PPE (Personal Protective Equipment) and shall be worn everytime they are enter the site.
  • Gloves should be used when handling these products.
  • Eye protection should be worn. Any splashes to the skin or eyes should be washed off. In the event of prolonged irritation, seek medical advice.
  • The Safety Supervisor / Safety Manager shall ensure the workers understand the safety regulations and explain in detail in particular hazards, where the workers are working and the precaution to be taken their safety.

5.2  Environmental


  • All workers shall educate on good environmental management practices and well-disciplined to environment.
  • The garbage bin shall be provided at the working area and Supervisor shall ensure its must be collected regularly and disposed-off at the approved dumpsite.
  • Safety team shall ensure that no open burning of construction or domestic wastes is practiced.
  • All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil leakage that could harm to environment.

Method Statement -Turfing and Landscape

1.    INTRODUCTION
This method statement covers the following work activities associated with the requirement of the contract document for (your project's name).

It is intended to assist site personnel in carrying out the performance of the activities. It also serves to demonstrate to the client that we as the contractor understand the work scope and is capable of undertaking it.


2.    REFERENCES
2.1   Construction Drawing
2.2   Contract Specification


3.   EQUIPMENT
3.1 Back Pusher
3.2 Water Pump and Pipe
3.3 Drum / Water Tank
3.4 Lorry
3.5 One Tonne Roller Compactor


4.0 GRASS / PLANT
The materials should come from approved sources by the client/consultant. The Contractor shall arrange the nursery visit with the client/consultant to get the approved material before delivered to the site.

4.1 Topsoil
Topsoil is the original surface layer or soil from cultivated land or forest area. It does not generally include soil from swampy area, padi field or tin mining areas.

It is usually a darker shade of brown, grey or red than the subsoil that lies immediately beneath it. Topsoil tends to be friable and show some degree of porosity. It should be free from subsoil, admixture of stones, lumps, plants or roots and other extraneous matter. Topsoil shall not deliver or used while in a muddy condition.


4.2 Axonupus Compressus (Cow Grass)
The grass should come from approved sources. The grass sod shall be cut and supplied at the approximate size 300mm square and minimum thickness shall be 50mm with original soil adhering to the roots.

The sods shall be free from weeds and shall be delivered to site and planted promptly to avoid desiccation.


5.0 METHOD OF PLANTING

5.1 Site Preparation
The Main Contractor is required to grade the planting area to finish grades and allowed for a smooth and uniform to the consultant approval. The Main Contractor is required to roll, scarify, rake and level so to obtain the even planting area. All loose stones, gravel, tree stumps in which is not desirable is required to cart away from site to the approved dumping area. To lay 50mm thick layer of approved black vegetable soil / top soil before turf.

5.2     Close Turfing
Turfing shall be carried out at all the terrace and slope area as specified (refer to the construction drawing).

The grass sod used for close turfing shall be cut and supplied at approximate size of 300mm square and minimum thickness 50mm with original sod adhering to the roots. The sods shall be 50% pure comprised of Axonupus Compressus. Close turfing shall consist of approximately 300mm square turfing laid side by side with gaps not exceeding 30mm. If necessary, each sod shall be stack with 200mm peg through the sod into the soil base, to prevent soil erosion.
               
The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but jointed as closed as possible to achieve a uniform cover. The turf shall be laid off planks working over turns previously laid. The whole area should present an even smooth surface when completed. Top dressing of the turf area shall be carried out immediately after the turf is laid and monthly intervals thereafter.

5.3     Spot Turfing       
Turfing shall be carried out to all the flat area as specified. The grass sod used for turfing shall be cut and supplied at approximate size of 300mm square and minimum thickness 50mm with original sod adhering to the roots.

The sods shall be 50% pure comprised of Axonupus Compressus. Spot turfing shall consists of approximately 300mm square turfing laid side by side with gaps on all sides of the turfing not exceeding 300mm. If necessary, each sod shall be stack with 200mm peg through the sod into soil base, to prevent soil erosion.

The sods shall be laid onto the surface of the prepared ground with leaf turfs upwards, but jointed as closed as possible to achieve a uniform cover. The turf shall be laid off planks working over turns previously laid. The whole area should present an even smooth surface when completed. Top dressing of the turf area shall be carried out immediately after the turf is laid and monthly intervals thereafter.

5.4       Planting of Bucida Molineti
The plant shall be of approved species shown on drawing and in healthy growing condition obtained from an approved source. Black earth shall consist of fertile top soil obtained from an approved source.  Generally all pits for planting of trees shall not be less than 750mm x 750mm deep, spaced at intervals as shown in the drawings or approved by E.R. the bottom and side of pits shall first be filled with layer of black earth before transplanting.

5.5       Watering
Watering shall be carried out immediately after the completion of planting. The completed areas shall be lightly sprayed with water and keep the areas moist.

5.6       Maintenance
Maintenance shall begin immediately after each portion of turfed and planting area is installed and shall continue for the period of maintenance as specified commencing from the date of acceptance. Maintenance is including watering, fertilizing, spraying and mowing.

·         Watering (Cow Grass and Bucida Molineti)
Watering is required to soak and penetrate the soil at a rate that will prevent saturation of the soil. The rate of application shall be not less than 2.7 litre per square meter and on no account shall turf be watered sparingly. During dry weather, shall be watered within 2 days of laying and subsequently once a week.

·         Weeding (Cow Grass)
Keep all planting area free from weed and undesirable grasses, by a method and by materials approved by client / E.R / Consultant.



·         Mowing (Cow Grass)
Mowing on newly established turfed areas should be delayed until it is obvious that the grass is growing strongly. The grass should be cut when they are about 50mm – 75mm in height can be gradually lowered at subsequent mowing until the height of 25mm to 40mm is achieved. Remove the grass clipping during or immediately after mowing.

·         Top Dressing (Cow Grass)
After established turfed areas, determine the evenness of the ground level and if any uneven ground level the top dressing shall be applied. Mixed river sand and topsoil will be filled up to the uneven area and also to any visible gap between sods.

·         Protection (Cow Grass)
Maintenance shall include all temporary protection of all turfing areas from trespassing and damage at all times. If any portion of turfed area is damaged, it shall be treated and replace.

·         Fertilizer Application (Cow Grass)
Fertilizer shall be Christmas Island Rock Phosphate or its equivalent applies at the rate of 34gms per square meter with the approval of Consultant after planted until 6 months.

NPK 15:15:15 shall be used after 3 months planted at the rate of 100gms per square meter and continue the application every 3 months.

·         Fertilizer Application (Bucida Molineti)
Fertilizer shall be Christmas Island Rock Phosphate or its equivalent applies at the rate of 0.3kg per square meter with the approval of Consultant prior to planting, spread evenly in pit base.

NPK 15:15:15 shall be used at the rate of 200gms for each plant every month for the first year period. For the next year after, fertilizing shall be continued every 4 months. This fertilizer must be applied around the plant, outside the canopy area.

·         Supporting Wood (Bucida Molineti)
Supporting wood shall be used to support the plant, depend on the plant size.

·         Pruning (Bucida Molineti)
Pruning shall apply from surface area.

·         Control Diseases and Pests (Bucida Molineti)
Watering and cleaning the affected area at the plant. Cut and remove branches that were attacked by worms and insects.

5.7       Handing Over
Main Contractor shall arrange joint site inspection for handing over after the end of the period maintenance. Main Contractor shall be carried out rectification works for any defect works.


6.0   SAFETY

6.1       Safety
1)            The workers shall provide with PPE (Personal Protective Equipment) and shall be worn all the time.
2)            During fertilizer work, the workers shall provide additional equipment such as safety goggles and mouth and nose filters to avoid contact with fertilizer.
3)            Site safety member should be available at all the time.

6.2       Environmental
1)                 The Contractor shall ensure no open burning is allowed at the site.
2)                 All the waste shall be collected and disposed correctly.

3)                 The Contractor shall ensure there is no oil leakages from machinery (cutting machine) which is could harm the environment.