1.0 OBJECTIVE
Outline the Method statement
for Concrete Repair - Honey Comb for structural element.
2.0 SCOPE OF WORK
This method statement shall be
used for structural repair for structural elements.
3.0 RESPONSIBILITY
Site Supervisor, Project Engineer
4.0 MATERIALS
·
Sika
MonoTop – 610MY
·
Sika
MonoTop – R
·
Sika
Grout 215
5.0 HANDLING AND STORAGE OF MATERIALS
Handling - Transport of
materials shall be carried out by lorry or other suitable machinery.
Storage – Covered and raised
above floor level.
6.0 PLANT, MACHINERY AND EQUIPMENT
Mixer machine, wheelbarrows,
wire brush, angle grinder, measuring tapes, and other handy tools.
7.0 PREPARATORY
WORKS
Obtain approved structural
repair layout and details from the client / client’s representative.
Submit inspection checklist for concrete
repair to client / client’s representative when carry out concrete repair
works.
8.0 WORK
METHODOLOGY
Method
1 – Re-cast Concrete Structure
i Identify and demarcate the member
which need to be demolished.
ii Erect adequate temporary props to
support the affected slab and beam.
iii Demolish the severe concrete structure
by means hacking with pneumatic tools. Ensure the edge of the concrete is
clean, sound and free from dirt or dust.
iv Care should be taken not to damage the
existing reinforcement of the beam and slab.
v Bonding Preparation - Apply one coat
of bonding agent Sika Monotop – 610MY
at the edge of existing concrete to receive new concrete.
vi Formwork – Erect formworks at the
demolished area and secure the formwork with suitable ties.
vii Request for inspection as per
inspection checklist for concreting
viii Pour ready-mixed concrete Grade 40 with
waterproofing admixture to the prepared formwork. Ensure the concrete have
sufficient vibration during concreting.
ix On completion carryout joint
inspection to sign on inspection checklist for post concrete.
Method
2 - Concrete Repair- Formwork Grouting
i.
Based
on structural repair layout, mark on existing structure such as concrete
honeycomb.
ii Surface Preparation - Cut and hack
around at demarcated honeycomb area with suitable tool and equipment. Ensure all loose concrete must be removed
down to sound concrete. (Note: Do not use an impact hammer greater than 15
pound)
iii Clean existing reinforcement and
clean/remove debris or loose concrete fragment from the rectification area.
iv Request for inspection as per
inspection checklist for concrete repair.
v Formwork –Install formworks that
cover the size of the repair area including place a layer of sponge at the
perimeter with suitable tied.
vi Install Inlet And Outlet - Drill two
rows (upper and lower part) of 25mmØ holes on the
formwork to insert 25mmØ
UPVC pipe with spacing of 600mm c/c.
vii Mix the pre-bagged polymer modified
shrinkage compensated high strength grout – Sika Grout with adequate water in a
mixing drum. 6mm to 10mm aggregate shall be added and mixed with the grout at a
ratio of 1:1 by weight to minimize heat generation.
viii The Sika Grout 215 concrete grout is
then poured into the pump. Pump the grout into the form work with the lowers
injection port until the grout is going out from the upper port.
ix Curing - Leave the formwork in place
for at least 24 hour. Upon removal of the formwork, cure the exposed surfaces
immediately with water.
x On completion carryout joint
inspection to sign on inspection checklist for concrete repair.
Method
3 - Concrete Repair- Formwork Grouting for honeycomb depth > 20mm
i Based on structural repair layout,
mark on existing structure such as concrete honeycomb.
ii Surface Preparation - Cut and hack
around at demarcated honeycomb area with suitable tool and equipment. Ensure all loose concrete must be removed
down to sound concrete. (Note: Do not use an impact hammer greater than 15
pound)
iii Clean existing reinforcement and clean/remove debris or loose concrete
fragment from the rectification area.
iv Request for inspection as per
inspection checklist for concrete repair.
v Formwork –Install formworks that
cover the size of the repair area including place a layer of sponge at the
perimeter with suitable tied.
vi Install Inlet And Outlet - Drill two
rows (upper and lower part) of 25mmØ holes on the
formwork to insert 25mmØ
UPVC pipe with spacing of 600mm c/c.
vii Flowable Sika Grout 215 - Place about
4.0 to 4.4 litres clean water into clean container; add the whole bag of Sika
Grout 215 (25kg) while continuously mixing. After mixing, stir lightly with a
spatula for few seconds to release any entrapped air.
viii The Sika Grout 215 concrete grout is
then poured into the pump. Pump the grout into the form work with the lowers
injection port until the grout is going out from the upper port.
ix Curing - Leave the formwork in place
for at least 24 hour. Upon removal of the formwork, cure the exposed surfaces
immediately with water.
x On completion carryout joint
inspection to sign on inspection checklist for concrete repair.
Method
4 - Concrete Hand Patch Repair (for area < 0.5m2 at depth < 20mm)
i Based on structural layout, mark on
existing structure such as concrete honeycomb.
ii Cut around demarcated honeycomb area
to eliminate feather edge.
iii Surface Preparation - Repair area shall
be clean, sound and free from all loosely adhering particles.
iv Bonding Preparation - Apply one coat
of bonding agent Sika Monotop – 610MY
“wet on wet” to the rectify area.
v Request for
inspection as per inspection checklist for concrete repair.
vi Concrete Mixing - The cement mortar Sika Monotop – R should be mixed in a clean drum. Place 3.4-3.5 litres of water
in to the drum and add Sika Monotop - R
slowly while mixing.
vii Application - Work wet on wet the mixed
mortar well into the rectify substrate, using a placing suitable tools, compact
well. Steel trowel the final coat if required.
viii On completion carryout joint inspection
to sign on inspection checklist for concrete repair.
9.0 SAFETY & ENVIRONMENTAL PROGRAMME
·
All HSSE procedure and
regulations shall be complied with.
·
To provide proper and safe
access for inspection and working.
·
Site personnel must be in
proper safety working attire e.g. Safety boots and helmets must be worn at all
times.
·
Proper and adequate
lighting to be provided when working at night.
·
Water ponding must be
constantly pumped out and mosquito infestation checked and controlled.
10.0 QA/QC PROGRAMME
10.1 Inspections and Test Plan
In order to ensure the
quality of honeycomb concrete repair works meet the requirement, inspection and
test shall be carried out as per the Project Quality Plan (PQP).
• Inspection Request Form (IRF) attached with Checklist
We Specialize in Aluminium Honeycomb Cores and Aluminium Honeycomb Panels. Our custom laminating and extensive material knowledge helps to provide our customers with infinite composite panel possibilities.
ReplyDeletehttp://www.alu-honeycomb-material.com/c/laser-cutting-platform-panel_0014
nice explanation about honeycomb in concrete
ReplyDeletetq =)
DeleteAll the contents you mentioned in post is too good and can be very useful. I will keep it in mind, thanks for sharing the information keep updating, looking forward for more posts.Thanks Nanaimo Drainage
ReplyDeletetq =)
DeleteReally a amazing info.. Thanks for posting.
ReplyDeleteWhether you require repairs for your potholes or advice on achieving better drainage on your driveway, our staff can help improve the safety and value of your property.
Construction Companies Winnipeg
Concrete Paver Winnipeg
tq =)
DeleteIts a great pleasure reading your post.Its full of information I am looking for and I love to post a comment that "The content of your post is awesome" Great work. concret York PA
ReplyDeletetq =)
Delete