1.0 OBJECTIVE OF PROCEDURE
This work method
statement covers the applying floor hardener at (affected building) for (your project name).
This work method
statement provides information concerning method of application to ensure
compliance with contract requirements and drawings besides to perform safe
working environment and compliance with safety requirements.
2.0 DESCRIPTION
PYEFLOOR
HARDENER NS is designed to provide a monolithic abrasion and impact resistant
floor finish. It is composed of selected silica quartz aggregates, cement and
plasticizer. PYEFLOOR HARDENER NS can be applied onto any concrete or
cementatious based substrate.
3.0 SEQUENCE OF WORK
4.0 WORK METHODOLOGY
4.1
Surface Preparation
Base concrete substrate must be fully compacted
with a grade of 30N/mm3 and a site slump test of 75 to 100mm. The
base concrete shall be stiffened, at an initial setting point, where light foot
traffic is allowed and does not leave a maximum of 5 mm deep imprint. However,
the timing shall not be too late until the moisture within the concrete is
sufficient to hydrate the PYEFLOOR HARDENER NS. Bleeding on the surface is to
be avoided.
4.2 Application
1.
Evenly broadcast about 60% of the material onto the base substrate.
2.
Wait until the colour of the PYEFLOOR HARDENER NS darkens from the
absorption of the moisture from the base substrate.
3.
Lightly compact the material using a mechanical power floating machine,
at a low speed, to prepare the surface for the second application of PYEFLOOR
HARDENER NS. Do not overwork the surface at this stage.
4.
Repeat the process again with the balance 40% of the material.
5.
Compact with mechanical power floating machine at a high speed until a
dense finish is achieved.
4.3 Curing
1.
Spray apply proper curing compound or use polyethylene sheet.
2.
Polyethylene sheet must be used to protect the floor finish surface in
case of rain.
5.0 SAFETY & ENVIRONMENTAL PROGRAMME
5.1 Safety
- All workers shall provide with PPE (Personal
Protective Equipment) and shall be worn every time they are entering the
site.
- Impervious gloves and barrier cream should be
used when handling these products.
- Eye protection should be worn. If accidental
eye contamination occurs, wash thoroughly with plenty of water and seek
medical advice.
- If the product contacted with skin occurs, it
must be removed before curing takes place. Wash out with an industrial
skin cleaner followed by plenty of soap & water.
- The Safety Supervisor / Safety Officer shall
ensure the workers understand the safety regulations and explain in detail
in particular hazards, where the workers are working and the precaution to
be taken their safety.
5.2 Environmental
- All workers shall educate on good
environmental management practices and well-disciplined to environment.
- The garbage bin shall be provided at the
working area and Supervisor shall ensure its must be collected regularly
and disposed-off at the approved dumpsite.
- Safety team shall ensure that no open burning
of construction or domestic wastes is practiced.
- All workers shall ensure that all tools and
equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.
- Spillage of component products should be
absorbed onto earth, sand or other inert material and transferred to a
suitable vessel. Disposal of such spillages or empty packaging should be
in accordance with local waste disposal authority regulations.
Ironite Floor Hardener
ReplyDeleteronite floor hardener
250 mesh iron oxide powder
200 mesh iron oxide powder
thank you for posting!Keep up your good work!
ReplyDelete
ReplyDeleteIam very happy to have such a blog here.I searched a lot and at last i find out the apt one..This blog is very informative for me and your knowledge about this topic is appreciable . Sohman Epoxy also contains a lot of information.This website also help me to deepen my knowledge..Just check this one also TH7301 surely you may get some more details about the topic.Thank you.