1.0
OBJECTIVE
This Work Method Statement is to outline the apply and lay pavement for
the road construction consisting of sub-base of granular material, road base of
crusher run, asphaltic concrete binder course and asphaltic concrete wearing
course.
2.0
SCOPE
This method statement shall apply for all
roadwork. The
intention of this work method statement is to give general guideline for the
roadwork construction. Details of the procedures contained herein may be
modified based upon actual ground condition and site requirements.
3.0
REFERENCES
•
JKR/SPJ/1988 Specifications Section 4
Spesifikasi Pembinaan Jalan
• Inspection Checklist for Roadwork
• Consultant’s Drawings
& Specifications
4.0
MACHINERY & EQUIPMENT
• Paving Set • Diamond
Cutter • Backhoe
• Back pusher • Tipper Lorries • Total Station
• Vibratory roller • Thermometer • Levelling
Instrument
5.0
MATERIAL
• Sand
• Crusher run
• Asphaltic Concrete Binder Course ACBC
28
• Asphaltic Concrete Wearing Course
ACBC 20
• Bituminous Prime Coat
• Bituminous Tack Coat
6.0
CONSTRUCTION PROCEDURE
6.1
General
6.1.1
Before
pavement construction can be allowed it is necessary for both the horizontal
and vertical alignment to be joint inspection and confirmed by the Consultant.
6.1.2
Surveyor
shall be using proper instrument total station and dumping level to mark on
site which is visible and protected during work construction.
6.1.3
Pavement
construction works shall only be allowed to commence on site upon the approval
and acceptance of the sub-grade layer.
6.1.4
The
Contractor shall counter check again the alignment and all dipping pegs and
confirm with the Consultant prior to the permanent work.
6.2
Work Sequence Flow
Laying 100mm granular material sub-base
|
Laying 200mm crusher run road base
|
Laying 60mm Asphaltic Concrete Binder Course
|
Laying 40mm Asphaltic Concrete Wearing Course
|
6.3
Preparation of Formation To Receive Road
Pavement
6.3.1
The
preparation of formation shall be carried out only after completion of piped or
box culvert, services, utilities and ducts (if any) or any other drainage work
that might affect the works, unless otherwise agreed by Consultant and such
preparation shall be carried out immediately prior to the laying of the
sub-base.
6.3.2
All the
materials for sub base, road base, ACBC and ACWC shall be sent to nominated and
approve laboratory to conduct necessary testing and to be comply with technical
specification.
6.3.3
The surface
of the formation shall be substantially uniform in density throughout its
entire width and shall conform to the density requirements for compaction. Trial
compaction to be conducted in order to determine the designated degree of
compaction as required with a present of supervision consultant.
6.3.4
Other
utilities crossing the road such as water mains and cables shall be protected
before proceed the road base works. For example using lid for u-drain and G.I.
conduit for cables.
6.3.5
It shall be
trimmed to conform to the lines, camber, grades and typical cross sections
shown on the drawings or as directed by Consultant.
6.3.6
The sample
of earth to send to lab for MDD test for comparison of degrees compaction.
6.3.7
To conduct
trial compaction to determine passes roller required.
6.3.8
Level
pegging to be done at suitable distance for inspection.
6.4
Earth Formation
6.4.1
Where soft
spots and unsuitable materials found, it shall be removed and backfilled with
approved suitable material and compacted in accordance to the agreed rolling
pattern.
6.5
Sub Base
6.5.1
The sub base
material shall be hard, durable and clean. It shall be granular material and
shall be free from organic material, clay balls, and any other deleterious
substances.
6.5.2
The
materials will be delivered to the site by tipper lorries and spread and
leveled by means of a back pusher for the full width of the pavement. The material
shall be filled and compacted to the required thickness as specified in the
drawing.
6.5.3
Compaction
of the sub base layer shall be carried out by using vibrating roller to achieve
relative dry density as per specification.
6.5.4
Alignment,
level and surface regularity will be checked in accordance to Technical
Specification.
6.5.5
The final
surface of granular sub base layer shall be regulated and trimmed by back pusher
to the required level and cross fall within the specified vertical tolerances. Compaction
work will be done using roller compactor.
6.5.6
Field
Density Test (FDT) or CBR Test on the subgrade shall be carried out according
to the specification.
6.6
Laying Road Base Material
6.6.1
The crusher
run road base to be placed on top of the sub base shall consisting of crushed
aggregate laid in layers each of thickness not exceeding 200mm and to give the
specified total compacted thickness and width, correct line and levels shown in
drawings.
6.6.2
The material
shall be crushed rock of hard durable particles or fragments of rock crushed to
the correct size, well graded and lie within the following grading limits specified
in the specification.
6.6.3
Care shall
be taken to prevent segregation of the material into the coarse and fine
fractions.
6.7
Bituminous Prime Coat and Tack Coat
6.7.1
An approve
bituminous prime coat which is submitted through material submission shall be
applied to the top of the completed crusher run base course before laying the
asphaltic concrete binder course.
6.7.2
The surface
shall be cleaned immediately prior to the application of prime coat. The
bituminous shall be applied by means of a distributor at suitable rates but not
to be less than 0.435 liters per sq meter. SS1K using for prime coat while RS1K
using for tack coat.
6.7.3
The surface
of the dense asphaltic concrete binder course shall be cleaned immediately
prior to the application of an approve tack coat. The bituminous shall be
applied by means of a distributor at suitable rates but not to be less than
0.35 liters per sq meter.
6.7.4
The prime
coat shall be sprayed well in advance and leave for 24 hours for curing.
6.8
Asphaltic Concrete Surfacing
6.8.1
General
The
surfacing shall be two courses and shall comprise of asphaltic concrete binder
course and Asphaltic concrete wearing course and lay in accordance with BS
1621. The two courses shall be constructed to the width and thickness after
compaction as shown in the drawing.
6.8.2
Material
1)
Course
Aggregate
Course
aggregate shall be hard un-weathered, durable, clean crushed rock, angular in
shape, free from dust and tested in accordance with the methods described in
B.S. 812.
2)
Fine
aggregate
Fine
aggregate shall be approved clean natural bank, river, dune, pit or quarry sand
produced in a secondary plant. They shall consist of hard, non-absorbent sharp
grains and shall be free from clay, loam, loosely bounded aggregations and
other foreign matters.
3)
Filler
Filler shall
be either Portland Cement complying with B.S. 12 or limestone, having a bulk
density in Toluene.
6.9
Asphaltic Concrete Binder Course, ACBC 28
6.9.1
ACBC 28 mix
will follow the approved mix design and trial mix.
6.9.1.1 The
aggregates shall be surface dry and shall be mixed at an appropriate
temperature. The mixed material as delivered to the laying site shall be
between 140 degrees Celsius to 160 degrees Celsius.
6.9.2
Laying
Procedure
6.9.2.1
Work shall
commence on site upon approval and acceptance of the road base.
6.9.2.2
The surface
to receive the asphaltic concrete binder course shall be free of all damage,
loose materials and standing water by sweeping.
6.9.2.3
Prime coat
of approved bitumen emulsion shall be applied as per Specifications on the
prepared surface prior to lay of the asphaltic binder course.
6.9.2.4
The
asphaltic concrete binder shall be plant mixed with approved bitumen content.
6.9.2.5
The approved
asphaltic concrete binder course shall be delivered to site by tipper trucks.
To prevent the loss of heat, the mixture shall covered by tarpaulin.
6.9.2.6
The asphaltic concrete binder course shall be laid
by a paver in single layer.
6.9.2.7
Compaction
shall be carried out using the specified equivalent type of compactors. Rolling
shall always commence from the lower to the higher side of the carriageway. The
minimum rolling temperature shall be 80 degrees Celsius.
6.9.2.8
The surface
of asphaltic concrete binder course shall be finished to the line and grade as
required by the Drawings.
6.10
Asphaltic Concrete Wearing Course ACWC20
6.10.1
ACWC 20 mix
will follow the approved design mix and trial mix.
6.10.1.1
The
aggregates shall be surface dry and shall be mixed at an appropriate
temperature. The mixed material as delivered to the laying site shall be
between 140 degrees Celsius to 160 degrees Celsius.
6.10.2
Laying
Procedures
6.10.2.1 Work shall
commence on site upon approval and acceptance of the asphaltic concrete binder
course.
6.10.2.2
The surface
to receive the asphaltic concrete wearing course shall be free of all damage,
loose materials and standing water by sweeping.
6.10.2.3
Tack coat of
approved bitumen emulsion shall be applied as per Specifications on the
prepared surface prior to lay of the asphaltic wearing course.
6.10.2.4
The
asphaltic concrete wearing shall be plant mixed with bitumen content.
6.10.2.5
The approved
asphaltic wearing course shall be delivered to site by tipper trucks. To
prevent the loss of heat, the mixture shall covered by tarpaulin.
6.10.2.6
The asphaltic concrete wearing course shall be laid
by a paver in single layer.
6.10.2.7
Compaction
shall be carried out using the specified equivalent type of compactors. Rolling
shall always commence from the lower to the higher side of the carriageway. The
minimum rolling temperature shall be 125 degrees Celsius.
6.10.2.8
The surface
of asphaltic concrete wearing course shall be finished to the line and grade as
required by the Drawings.
6.10.2.9
Upon
completion of laying and compaction, joint survey shall be carried out to check
for compliance with the specified requirement.
6.10.2.10
After all
the above works is completed, the supervisor is to ensure that the site is to
be tidied up and all excess materials are to be discarded away from the site.
6.11
Transporting
6.11.1
Bituminous
materials shall be transported in clean vehicles and shall be covered over when
in transit or awaiting tipping.
6.11.2
Every
precaution is to be taken to avoid segregation of mixed materials and to ensure
that they do not become contaminated with foreign matter.
6.11.3
In order to
maintain satisfactory temperatures of materials in transit and to prevent undue
loss of heat adequate precautions are to be taken to ensure that the materials
are properly protected.
6.12
Laying
6.12.1
The mixed
materials shall, as soon as possible after arrival at the laying site, be
supplied continuously to the paver and laid without delay
6.12.2
Wherever
practicable, road pavement materials having bitumen as the binder shall be
spread, leveled and tamped by approved self-propelled pavers capable of laying
to the required width, profile, camber or cross fall.
6.12.3
Immediately
after any course is placed and before rolling is started, the surface shall be
checked and all defects and irregularities in alignment, grade or texture
corrected by the additional or removal of mixture.
6.13
Compaction
6.13.1
The
compaction shall be compacted as soon as possible as rolling can be effected
without causing undue displacement of the mixed material.
6.13.2
The rollers
shall be fitted with beeper.
6.13.3
The
materials shall be rolled in longitudinal direction from the sides to the
centre of the carriageway.
6.13.4
For
compaction, two times rolls pass by non-vibrate compactor prior to two times
rolls pass by vibrate compactor. The roller shall weigh not less than 12
tonnes.
6.13.5
Eight times
rolls pass compaction shall be carried out by tyre roller.
6.13.6
The last
compaction shall be done by non-vibrate compactor.
7.0
Safety And Environment
7.1
Safety
7.1.1
Safety induction to be conducted to all
new workers that involved to this activity and safety toll box meeting shall be
conducted every day to remind the workers about concerning the safety.
7.1.2
All workers shall be provided with PPE
(Personal Protective Equipment) and shall be worn at all time on site. Safety
Manager / Safety Supervisor shallensure all the workers wear all the safety
equipments provided.
7.1.3
All workers shall be advised to report
any accident or injury to supervisor.
7.1.4
Proper and adequate provision of
temporary signage’s and barricades at diversions and temporary haul road as
necessary (if applicable).
7.2
Environment
7.2.1
All workers shall educate on good
environmental management practices and well disciplined to environment.
7.2.2
The garbage bin shall be provided at
the working area and Supervisor shall ensure its must be collected regularly
and disposed off at the approved dumpsite.
7.2.3
All workers shall ensure that all tools
and equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.
Much appreciated
ReplyDeletebaik arh!!
ReplyDeleteGood work
ReplyDeleteBoleh email ke sy softcopy method statement ni ? firdaus@ikram.com.my
ReplyDeleteThis is helpful thanks for the post.
ReplyDeleteNice info
ReplyDeleteThank You
Good Info and very clear explanation
ReplyDeletethanks
Good.
ReplyDeleteAny other method of statement
ROAD MARKING ADE?
ReplyDelete