1. OBJECTIVE
To outline the sequence of activities, method and resources needed for
the operation of erecting temporary hoarding.
2. SCOPE
The work shall include all labour, material, equipment, safety
requirement and services necessary for the execution erecting temporary
hoarding.
3. WORK SEQUENCE FLOW
_to attach drawing_
4. MATERIAL
Material to be used is as follows:-
4.1 50 x 50 x 1.6mm thick SHS M.S Posts
4.2 50 x 25 x 1.2mm thick RHS M.S Nogging
4.2 50 x 25 x 1.6mm thick SHS M.S Braces
4.3 0.3mm thick metal decking
4.4 Nail
4.5 Cement
4.6 Sand
4.7 Water
5. EQUIPMENTS & MACHINERIES
REQUIRED
Equipments and
machineries to be used are as follows:-
5.1 Minimum: One (1) number of JCB Backhoe
(if required)
5.2 Minimum: One (1) set of hand
excavating equipment
5.3 Minimum: One (1) set of steel work
equipment
5.4 Minimum: One (1) set of water levelling
5.5 Minimum: One (1) number of spirit
level
6. SITE PREPARATION WORK
6.1 Setting out boundaries of ground in
the proposed perimeter.
7. METHOD OF WORK
7.1 Determine the location of the
temporary hoarding will be established with confirmation from the surveyor.
7.2 After getting confirmation, using the
given point and
mark the main pole as per alignment shown in the drawings (Appendix
A). Center to center of the main column
is 3000mm.
7.3 Preparation of the main pillars started by
using hand digging to the depth 400mm.
7.4 Pole-sized 50X50X1.6mm thk SHS M.S constructed using equipment such as spirit level, water
level, and tape
measure. Two workers used to
establish the main pillars.
7.5 Pillars need to ensure accurate position along the
fence line at
3.0m (panel width)
intervals and make sure the base are sitting on an even level surface.
7.6 Erect the remaining pillars
along the line
as noted previously until the hoarding line
is complete.
7.7 50x25x1.2mm thk nogging need to
install three (3) lines to support metal deck panels.
7.8 Metal deck panels will be
installed with the frame hoarding
as per Appendix A (spacing 4” for every panels).
7.9 This work will be
repeated until completion.
7.10 Entrance gate
will be erected at remaining area (refer item no.3) with support at both side
(left and right) using welded angles.
8. QUALITY ISSUES
·
Boundaries demarcation
required to ensure no double handling or trespassing to others people land.
·
View inspection
required during the process of erection hoarding.
·
Regular inspection
to be carried out by weekly basis to ensure the hoarding in good condition.
9. SAFETY ISSUES
·
Safety helmets and
safety footwear should always be worn.
·
All soft spots or
holes shall be identified and barricade if necessary.
·
The site shall be
kept clear of unnecessary obstruction.
·
First aid kit
boxes will be provided at site office.
·
During raining, no
erection hoarding activities are allowed to work.
10. ENVIRONMENTAL ISSUES
·
All workers shall
ensure that tools and machinery are in a good condition to avoid any oil
leakage that could harm to environment.
·
Construction waste
from construction area must be collected into centralized garbage bin and
disposed at the designated area.
And across the street is where Farm 18 is going. 7.5 acres of glory, unspoken for as of yet.cedar fence installation
ReplyDeleteHiring the right services for such and other needs like cheap fencing in Melbourne is a viable choice to make and you will be glad to have found them by going over the internet. The prices are right and the offered services will be best in class and affordable as well. wood fence styles
ReplyDeletei need method statement for lowering of existing electrical cable from proposed storm water line.please give me the procured.
ReplyDeletethanks