1.0
|
OBJECTIVE
|
||||||||
To
outline the method statement for Wireless Telephone Installation (IP base
PABX system)
|
|||||||||
2.0
|
SCOPE
|
||||||||
To
supply, install, programming an IP base PABX system ready type c/w built-in
UPS for back-up upon
|
|||||||||
failure
up to 4 hours, voltage stabilizer, over voltage surge arrestor, with expandable to 500 ports
|
|||||||||
extension
and all necessary accessories, as per drawing and specification.
|
|||||||||
|
|||||||||
3.0
|
REFERENCE
|
||||||||
·
Project Specification.
|
|||||||||
·
Carrying out Construction / Installation
works procedure inspection and test plan, inspection check list, etc.
|
|||||||||
|
·
Proposal drawing from specialist.
|
||||||||
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
4.0
|
RESPONSIBILITIES
|
||||||||
·
Engineer
|
|
|
|||||||
·
Supervisor
|
|||||||||
5.0
|
MATERIALS
|
||||||||
·
NEC SV8100 Series Business Features
(Primary)
·
NEC SV8100 Series Business Features
(Secondary)
·
Terminal (Operator)
·
Terminal (Office Staff)
·
OCS System
|
|||||||||
6.0
|
HANDLING AND STORAGE OF MATERIALS
|
||||||||
Handling:
|
All materials received at site shall be
checked according to the Delivery Order (D.O) and Purchase Order to ensure
the materials received are in conformance.
|
||||||||
|
|
||||||||
Storage:
|
Deliver the products to the protected area
and stack / arrange the materials in a flat and dry surface place.
|
||||||||
7.0
|
PLANT, MACHINERY, EQUIPMENT AND TOOLS
|
||||||||
a.
|
Safety
gears
|
||||||||
b.
|
Transportation
i.e. Van, pickup truck
|
||||||||
c.
|
Basic
hand tools (Needle nose pliers, wire stripper, network interface wire
junction etc.)
|
||||||||
d.
|
Scaffolding
|
||||||||
|
|||||||||
8.0
|
PREPARATORY WORKS
|
||||||||
8.1
|
All installation works is according to the
approved shop drawing and technical specification.
|
||||||||
8.2
|
Any deviation at site from the approved shop
drawings shall seek the confirmation and clarification from
|
||||||||
Consultant or reported to Employer's
Representative for approval on new proposal.
|
|||||||||
9.0
|
WORK METHODOLOGY PROCEDURES
|
||||||||
9.1
|
General construction and installation of
wireless telephone system.
|
||||||||
9.1.1
|
Site clearance.
|
||||||||
9.1.2
|
Documentation
and drawing plan
|
||||||||
Prepare
and submit to Consultant the presentation and approved by Consultant.
|
|||||||||
9.1.3
|
Deliver
of materials on site
|
||||||||
9.1.4
|
Checking
of parts and materials on site
|
||||||||
9.1.5
|
Pre-requirement
of installation
|
||||||||
M&E
installation (such as of cable and trunking) being completed and Main
Contractor is to ensure that the
|
|||||||||
room
is free from construction debris.
|
|||||||||
9.1.6
|
Installation of wireless telephone
system/Main PABX
|
||||||||
a.
|
Location
of server and modem is determined at the management office.
|
||||||||
b.
|
Ensure
the wireless system component part and etc. as per submitted of functional
system shop drawings.
|
||||||||
c.
|
All
cable termination into such as incoming and outgoing cable is terminated by
insertion tool.
|
||||||||
d.
|
Programming
of PABX system
|
||||||||
9.1.7
|
Installation
and checking of grounding and surge protectors
|
||||||||
9.1.8
|
Installation
and testing of the PABX to end user(wireless mode)
|
||||||||
9.1.9
|
Prepare
documentation and user training
|
||||||||
|
|||||||||
10.0
|
TESTING PROCEDURES
|
||||||||
Testing
, commissioning and configuration the following systems and guarantee full
functionality of the
|
|||||||||
system
during defect and liability period as per scope of works & according to
the requirements
|
|||||||||
and
specifications of ECER. (Contractor need to carry out pre-T&C for all the
systems and submit the
|
|||||||||
test
results to ECER before T&C with ECER.
|
|||||||||
·
Check the system batteries and connection
of cables.
·
Check the polarity of batteries cables and
ensure color code for positive and negative.
·
Check the installation between the
batteries back up and PABX.
·
Measure the line voltage to the charger and
ensure that the voltage is 220v with maximum of 5% up or down.
·
Ensure the approval and acceptance of the
telephone numbering plan by the Consultant.
·
Upon completion of the above the PABX agent
will start up the PABX and start the start up check of all the boards and
hardware.
·
Programming of the PABX will start
according to the approved numbering plan, telephone numbers not to be changed
to avoid destroying the PABX program.
|
|||||||||
11.0
|
SAFETY FEATURES
|
||||||||
All operation during this work will be done
in an efficient and safe manner and in accordance to the Safety
|
|||||||||
procedures.
However, there are issues concerning safety for this work that are to
be observed base on the
|
|||||||||
results of the audit, relevant safety
measures will be proposed and implemented.
|
|||||||||
a.
|
Carry
out a Hazard Identification Audit (HIA) before start of work each day and
before the start of new task.
|
||||||||
b.
|
The
material shall be in good condition, clean and free from defect and crack
during the installation.
|
||||||||
c.
|
All
material shall be transported by lorry to the site. Upon arrival, the materials shall be
unloaded at our
|
||||||||
storage
yard, either manually or by machinery.
All material shall be check and inspected by the Supervisor
|
|||||||||
and
Consultant. The materials are
carefully stacked on timber and cover with non-staining plastic sheet.
|
|||||||||
|
|||||||||
12.0
|
VERIFICATION CHECK LIST
|
||||||||
Based
on proposal drawing.
|
|||||||||
13.0
|
RECORDING
|
||||||||
Request for inspection form (as per
attachment form)
|
SAYA HALALKAN SEGALA MAKLUMAT/INFO INI UNTUK RUJUKAN KALIAN
Tuesday, June 3, 2014
Method Statement -Installation of Wireless Telephone System
Subscribe to:
Post Comments (Atom)
Thank you for sharing,,,, mypbx
ReplyDeleteU r wc... ^^
DeleteReally very awesome post and also you have share all methods of Nec SV8100 phones thank u so much...
ReplyDeleteWellcome sis.. Sharing is the best way to spread our knowledge.. Bcoz Im not a teacher/lecturer... ^^
Delete