jika kau fikirkan kau boleh! kau hampir boleh melakukan.. jika kau fikirkan ragu-ragu, usahamu tak menentu.. jika kau fikirkan kemenangan, kau menghampiri kejayaan.. jika kau fikirkan kekalahan, kau hampiri kegagalan.. renung-renungkan ~

Saturday, December 14, 2013

Method Statement -Anti-Termite

1.              1 .         OBJECTIVE

To outline the sequence of activities, method and resources needed for the operation of
anti-termite soil treatment work.

Soil treatment to protect new buildings against subterranean termites attack should be carried out strictly in accordance with one of the reorganized international codes of anti-termites treatment practice.


2.         SCOPE

The work shall include all labour, material, equipment, safety requirement and services necessary for the execution anti-termite soil treatment work.

Anti-termite treatment is carried out under the Malaysian Standard code of Recommended Practice for soil Treatment of Protection of Building against Subterranean Termites. This code set out a recommended practice for the chemical treatment for the protection of building from attacks by subterranean termites. It includes reference to the chemical used, lay down minimum rates of application for usage and outlines procedures to be followed.

It covers the entire floor area including the aprons with a specially formulated chemical to create an impregnated unbroken barrier.


3.         MATERIAL
           
            Material to be used is as follows:-
               
                3.1          Anti termite chemical – Chlorpyrifos (Termi Force 21.2/Chemicide 75+)


4.         EQUIPMENTS & MACHINERIES REQUIRED

                Equipments and machineries to be used are as follows:-

4.1          Minimum: One (1) no. of power spray pump set (6.3)
                4.2          Minimum: One (1) no. of rubber glove
                4.3          Minimum: One (1) no. of safety glasses
                4.4          Minimum: One (1) no. of mask
4.5          Minimum: One (1) no. of 200 liter water tank
  

5.         SITE PREPARATION WORK

5.1          The removal of free stamps, logs or roots from building site reduces the hazard from white ants. Similarly the sub-floor area should be kept free from all debris in which new colonies of termite might be established.

5.2          Anti-termite treatment should be carried out at the stage of the construction when the whole sub-floor area is readily accessible and there is little chance of subsequent soil disturbance, in general, this will be immediately before the slab is poured in case of lean concrete floor.


6.         WORK SEQUENCE AND METHOD

            6.1          Determine the location of the anti-termite treatment to lay (Silage Store).

62           Chemical Usage
               
6.2.1      Formulation – The latest anti-termite Chlorpyrifos with an active ingredient 21.2% which is recommended internationally for Termite Treatment.  It is suggested by Pest Control Association of Malaysia (PCAM) and approved by Pesticide Board of Malaysia.

6.2.2      Chemical Application
·         Rate of application (liters) – 1 liter of Chlorpyrifos : 40 liters of water (1:40)
·         Method of application (liters) – 4.5 to 5 liters of mixed termiticide per square meter.


6.3          Method of Spraying
·         Power spray with high pressure will be used to spray along perimeter of footing and ground beam/wall of the silage store and within built up area with a mixture of 1:40 as recommended by chemical manufacturer.

6.4       The anti-termite treatment shall be started when backfilling and compaction works for ground floor is completed.

6.5          Lean concreting for ground floor slab will start after impregnation the areas with the anti-termite chemical.


7.            QUALITY ISSUES

·      The anti-termite chemical shall be applied in accordance with the manufacturer’s recommendation and label instruction.

·         The minimum surface application rate shall be 5 L/m2 on all ground floors built-up areas including apron areas and also on all areas extending 1.0m beyond the perimeter drain all around the building.

·     The anti-termite chemical shall be sprayed on interfaces between the concrete ground beam and the hardcore at minimum rate of 1 litre per linear meter.

·     Treatment shall not be performed just before or after heavy rain unless the area to be treated can be physically protected as rain may cause leaching and run off before the anti-termite chemical has bound to the soil.

·         Immediately after spraying of chemical, all surface exposed to direct sunlight or rain shall be covered with the building concrete of polythene damp-proof membrane.

·       Upon completion of the entire job, the applicator will issue a warranty valid for TWO-(2) years starting from obtained of CPC. Under this warranty, we will provide quarterly inspections on the treated building. PRIMA PEST CONTROL AND SERVICES will undertake to treat any subterranean termite’s re-infestation without within the warranty period.

·     Any alteration or extension work to the existing building which may result breaching, bridging or bleaching of the treated soil laterally or vertically has to be notified to us for further consultation. Otherwise, the warranty is void and null.


8.         SAFETY ISSUES

·         Safety helmets and safety footwear should always be worn.

·         All soft spots or holes shall be identified and barricade if necessary.

·         Rubber glove, mask and safety glasses should always be worn.

·         The site shall be kept clear of unnecessary obstruction.

·         First aid kit boxes will be provided at site office.

·         During raining, no activities are allowed to work.

·         Unauthorized personnel are not permitted within the construction area.

·         All work will be done by in a safe working environment.


9.         ENVIRONMENTAL ISSUES

·         All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil leakage that could harm to environment.

·         Water from particular construction area shall be diverted into proper drain which is eventually empties into silt trap.

·         Domestic and construction waste from construction area must be collected into centralized garbage bin and disposed at the designated area.

Method Statement -Site Clearing

1.0 OBJECTIVE
     
To outline the method statements by which the site clearing is carried out. This work method statement covers the clearing works at (your project name).


2.0 SCOPE

This method statement shall apply for site clearing work in (the affected area) as per bill of quantities where it require to cut and uprooting the trees, clearing of bushes and cut the trees on the slope area.


3.0 REFERENCES

·                Construction Drawings
·                Project Specifications
·                Surveying Field Book


4.0 DEFINITIONS
       -Nil


5.0 RESPONSIBILITIES

·                Safety Officer/Supervisor
·                Site Engineer
·                Site Supervisor


6.0 MATERIALS
       -Nil


7.0 HANDLING AND STORAGE OF MATERIALS
       -Nil


8.0 PLANT, MACHINERY AND EQUIPMENT

·                Excavators
·                Lorries
·                Chainsaw

9.0 PREPARATORY WORKS

9.1      Obtain relevant approved construction drawings from client / client’s representative.
9.2      The site will be visited in order to acquaint nature, extent and practicality of the site clearing and temporary works. Surveyor shall take the existing ground and formation levels as required are correct.
9.2      Set out the location, center line, right of way and limits of works to minimize exposed areas and prevent additional clearing.


10.0 WORK METHODOLOGY

10.1    Where necessary, prepare access to the area to be cleared.
10.2    Shrubs, bushes and trees are cleared using excavators and bulldozers / other approved machineries.
10.3    All the cleared trees and shrubs are piled and placed at convenient places.
10.4    The cleared trees and shrubs are then loaded on to lorries and disposed at approved disposal site. Maintain records of disposal records at relevant inspection checklist.
10.5    Submit Request for Inspection Form for joint inspection and record joint measurement with client / client’s representative in Surveying Record Book.
10.6    On completion of joint inspection, request client / client’s representative to sign on the Request for Inspection Form and file as per Project Filing Index.
10.7    Carry out computation and submit for claim.


11.0 TRAFFIC MANAGEMENT AND MONITORING

11.1 Maintenance of Existing Roads, Footpaths and Service Drains, Etc.

The construction team shall maintain all existing site excess, roads, footpath, service drain, etc. and reinstate any damage caused by any reason whatsoever during the progress of the works.

It will be the Safety Officer/Supervisor’s responsibility to ensure that ingress and egress to the site are kept free from obstruction brought about by the work on this site and in no way shall cause hindrance to traffic or ancillary works either by his own vehicles or by his work people, material, etc.


12.0 SAFETY PROGRAMME

12.1    Temporary Works and Public Safety

The Safety Officer/Supervisor shall be responsible for submission of plans and drawings to the relevant Authorities for the construction of all the necessary temporary drains and desilting pits, safety nettings for the works.

The Safety Officer/Supervisor shall provide adequate signboards at all strategic positions warning the public to keep away from the work site and erect temporary fencing and barriers where necessary around the site to prevent unauthorized trespassing during works.


13.0ENVIRONMENTAL PROGRAMME

All works should be carried out in accordance to best practice environmental management as defined in the EMP for the Construction Phase of the Muadzam Shah Cattle Research and Innovation Centre.

13.1    Site Access.

The access as well as the portion of public road and walkway connected with it shall be kept clean and safe at all time.

13.2    Temporary Work.

Existing drain shall be identified by contractor together with the flow of drain until discharge point in order to make use of it during clearing work. Silt trap shall be provided before any discharge of surface water within site towards existing drain. This work should be completed prior to the commencement of any site clearing activities.

Temporary earth drain shall be constructed along clearing area to retain the surface water from dismissal directly towards existing drain. Desilting work shall be carried out regularly and the existing drain will be maintained during site clearing work.

As the slope area will not be disturbed, the existing turf or grown grass shall be remain and only manually cut the grown trees without uprooting it. Plastic sheet /canvas will be provided on site on standby basis in order to be use as slope protection if necessary.

Any effluent discharges from the site must comply with the Third Schedule of the Environmental Quality (Sewage and Industrial Effulents) Regulation 1979.


13.3       Waste Management.


Any construction wastes, solid wastes and domestic wastes other than schedule wastes must be disposed off at the approved disposal site. On site compositing for biodegradable waste is allowable but land filling and open burning activities for the solid waste are strictly prohibited.

Method Statement -Water Reticulation Works

1.0               INTRODUCTION
This work method statement covers the water reticulation works at (your project name).

2.0               SCOPE OF WORKS
The works to be carried comprise of:
a)                  Clearing and preparing the ground for laying the 100mm dia. HDPE main pipe and constructing all ancillary works.
b)                  Excavating and preparing trenches and foundations to receive the main pipe, pipe piers or supports, chambers and other ancillary works including backfilling and disposing of excess spoils.
c)                   Construction pipe piers or supports, anchor blocks and chambers.
d)                  Supplying, laying and jointing pipes, specials, valves and other fittings.
e)                   Pressure test of installed pipes and necessary fitting.

All works shall comply with the requirement of Local Authorities and where required the plumber responsible for the execution of the work shall be a licensed plumber. The Contractor shall execute the works in strict conformity with the approved plans and shall arrange for the necessary formalities to be complied with.

3.0          WORK SEQUENCE FLOW

4.0          PREPARATORY WORKS
Obtain relevant approved construction drawings, shop drawings and materials from client / client’s representatives. Submit Request for Work Inspection to inform consultant before proceed the work. Since the approved material received to site, all materials are to be inspected and possible damages must be reported on the delivery note.
                                                                                                                                               
5.0          METHOD STATEMENT

5.1          SURVEY, SETTING OUT AND EXCAVATION OF TRENCH

The Contractor shall excavate to the line and levels as shown in the drawings, or as directed by E.R. The Contractor shall carry out all excavations in such manner and order as approved by the E.R and in whatever material as may be found. All excavations shall be carried out to the required lengths, widths, depths, inclinations or curvatures as may be necessary for the proper construction of the works or as shown on the drawings. All excavations shall be sufficient to provide for the necessary working space.

The bottom of all excavations shall be carefully trimmed and levelled, well rammed and consolidated to ensure good solid foundations. Before commencing the excavation of pipe trenches, the routes of the pipelines shall be pegged out accurately.

Where the pipes are to be laid on a concrete bed, the width of the excavation at the bottom of the trench shall be the width of the underside of the concrete bed.  The trench shall be excavated to the depths intended or shown in the drawings and shall be finished and trimmed accurately to level.

The Contractor shall lay sand since the trench is ready to receive the pipe. The bedding detail shall refer to the drawing.

5.2          LAYING PIPES AND FITTINGS

All pipes and fittings shall be laid to the lines and levels shown on the drawings or as otherwise directed by E.R. Before any pipe is lowered into the trench, it shall be cleaned and re-examined for cracks and flaws. If undamaged it shall be placed in position ready for jointing.  After laying, the interior of pipes shall be carefully cleaned again to remove any debris, dirt, stones or other matter that may have entered during laying.

Where the pipe lines encounter obstruction of laying such as drain, a galvanised iron pipe shall be used for crossing across the drain and exposed.


5.3          BACKFILLING OF PIPE TRENCH AND COMPACTION

After the pipe laying has been approved by the E.R and before the pipelines are tested, only sufficient backfilling of the trenches to prevent ‘snaking’ and to maintain the pipes in position will be permitted, but all joints shall be left exposed. In backfilling pipe trenches, only approved materials free from stones or rocks or other hard materials shall be carefully spread along the trench bottom between the pipes and trench walls to a depth of about 150mm thick of the same materials shall be hand rammed. Further layers each of about 150mm thick of the same materials shall then be spread and rammed in the same manner up to the top of the pipes. It shall be placed in layers each of 150mm thickness and hand or mechanically rammed until the backfill is 300mm above the top of the pipes.


5.4          TESTING OF PIPELINE

The Contractor shall provide all necessary equipment and material required for the purpose of testing work.

Test shall be carried out in the presence of a representative from Consultant or Pengurusan Air Pahang Berhad if required. No pavement will be made for pipe laying until the mains have been satisfactorily tested.

Wherever a section of any pipe has been laid, jointed and backfilled, it shall be prepared for testing by sealing the both ends temporarily with end cap. The end cap shall be of cast iron or steel. The end cap at the lower end or the section of the main shall be fitted with a valve inlet pipe for use to fill the section of the main with water and the stop end at the higher end of the section of the main shall be fitted with a valve air release vent pipe.
The test pressure to be applied shall be approximately 1.5 times the working pressure with details as shown in the drawings or as directed by E.R.

In testing, the main shall be filled with clean water and after a period of 24 hours, the pressure shall be raised by pumping to the specified test pressure. Pumping shall then cease and after a period of 3hours or a pressure fall of 9m whichever is sooner, pumping shall be resumed and the quantity required to be pumped, in order to restore the test pressure, divided by the time, shall be measure of the rate loss.

The length of main under test shall be deemed to have passed the test if the leakage does not exceed 0.05litres per mm of internal diameter per 24hours per kilometre of pipe length. If this specified rate of leakage is exceeded, a thorough inspection of the section of the main shall be made. All leaks discovered shall be repaired and the section shall be tested again.

The section of the main to be test shall be filled with water and the water shall be introduced into the section of the main through the valve inlet in the stop end at the lower end of the section. During filling provision shall be made for the air to escape from all high spots in the section by properly installing all air valves and from the air release vent pipe in the stop end at the higher end of the section.


 6.0          SAFETY AND ENVIRONMENT

6.1          Safety
1)            Safety induction to be conducted to all new workers that involved to this activity and safety tool box meeting shall be conducted every day to remind the workers about concerning the safety.
2)            All workers shall provide with proper PPE (Personal Protective Equipment) and shall be worn every time they are entering the site. Safety Officer / Safety Supervisor shall ensure all the workers wear all the safety equipment provided.
3)            Safety Officer / Safety Supervisor shall ensure that the activity shall carry out in a safe manner.
4)            All workers shall fully support and actively participate in all safety related activities and comply with all practicable safety measures.
5)            All workers shall be advised to report any accident or injury to supervisor and proper treatment to be obtained.
6)            The Safety Supervisor / Safety Officer shall ensure that the workers understand the safety regulations and explain in detail in particular hazards, where the workers are working and the precaution to be taken to ensure their safety.
7)            Proper and adequate provision of temporary signage’s and barricades at diversions and temporary haul road as necessary.

6.2          Environmental
1.            All workers shall educate on good environmental management practices and well-disciplined to environment.
2)            The garbage bin shall be provided at the working area and Supervisor shall ensure its must be collected regularly and disposed of at the approved dumpsite.
3)            Safety Officer/Supervisor shall ensure that no open burning of construction or domestic wastes is practiced.
4)                  All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil leakage that could harm to environment.

5)                  Open burning of construction and domestic wastes on the site premises are strictly prohibited.

Method Statement -Floor Hardener

1.0  OBJECTIVE OF PROCEDURE
This work method statement covers the applying floor hardener at (affected building) for (your project name).
This work method statement provides information concerning method of application to ensure compliance with contract requirements and drawings besides to perform safe working environment and compliance with safety requirements.

2.0  DESCRIPTION
PYEFLOOR HARDENER NS is designed to provide a monolithic abrasion and impact resistant floor finish. It is composed of selected silica quartz aggregates, cement and plasticizer. PYEFLOOR HARDENER NS can be applied onto any concrete or cementatious based substrate.

3.0  SEQUENCE OF WORK



4.0  WORK METHODOLOGY

4.1   Surface Preparation
Base concrete substrate must be fully compacted with a grade of 30N/mm3 and a site slump test of 75 to 100mm. The base concrete shall be stiffened, at an initial setting point, where light foot traffic is allowed and does not leave a maximum of 5 mm deep imprint. However, the timing shall not be too late until the moisture within the concrete is sufficient to hydrate the PYEFLOOR HARDENER NS. Bleeding on the surface is to be avoided.

4.2  Application
1.       Evenly broadcast about 60% of the material onto the base substrate.
2.       Wait until the colour of the PYEFLOOR HARDENER NS darkens from the absorption of the moisture from the base substrate.
3.       Lightly compact the material using a mechanical power floating machine, at a low speed, to prepare the surface for the second application of PYEFLOOR HARDENER NS. Do not overwork the surface at this stage.
4.       Repeat the process again with the balance 40% of the material.
5.       Compact with mechanical power floating machine at a high speed until a dense finish is achieved.

4.3  Curing
1.       Spray apply proper curing compound or use polyethylene sheet.
2.       Polyethylene sheet must be used to protect the floor finish surface in case of rain.


5.0  SAFETY & ENVIRONMENTAL PROGRAMME

5.1  Safety
  • All workers shall provide with PPE (Personal Protective Equipment) and shall be worn every time they are entering the site.
  • Impervious gloves and barrier cream should be used when handling these products.
  • Eye protection should be worn. If accidental eye contamination occurs, wash thoroughly with plenty of water and seek medical advice.
  • If the product contacted with skin occurs, it must be removed before curing takes place. Wash out with an industrial skin cleaner followed by plenty of soap & water.
  • The Safety Supervisor / Safety Officer shall ensure the workers understand the safety regulations and explain in detail in particular hazards, where the workers are working and the precaution to be taken their safety.
  
5.2  Environmental

  • All workers shall educate on good environmental management practices and well-disciplined to environment.
  • The garbage bin shall be provided at the working area and Supervisor shall ensure its must be collected regularly and disposed-off at the approved dumpsite.
  • Safety team shall ensure that no open burning of construction or domestic wastes is practiced.
  • All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil leakage that could harm to environment.
  • Spillage of component products should be absorbed onto earth, sand or other inert material and transferred to a suitable vessel. Disposal of such spillages or empty packaging should be in accordance with local waste disposal authority regulations.