1.0
OBJECTIVE
To outline the method statements by which
the site clearing is carried out. This work method statement covers the clearing
works at (your project name).
2.0
SCOPE
This method statement shall apply for site
clearing work in (the affected area)
as per bill of quantities where it require to cut and uprooting the trees,
clearing of bushes and cut the trees on the slope area.
3.0
REFERENCES
·
Construction
Drawings
·
Project Specifications
·
Surveying
Field Book
4.0
DEFINITIONS
-Nil
5.0
RESPONSIBILITIES
·
Safety
Officer/Supervisor
·
Site Engineer
·
Site
Supervisor
6.0
MATERIALS
-Nil
7.0
HANDLING AND STORAGE OF MATERIALS
-Nil
8.0
PLANT, MACHINERY AND EQUIPMENT
·
Excavators
·
Lorries
·
Chainsaw
9.0
PREPARATORY WORKS
9.1 Obtain relevant approved construction
drawings from client / client’s representative.
9.2 The site will be visited in order to
acquaint nature, extent and practicality of the site clearing and temporary
works. Surveyor shall take the existing ground and formation levels as required
are correct.
9.2 Set out the location, center line, right
of way and limits of works to minimize exposed areas and prevent additional
clearing.
10.0
WORK METHODOLOGY
10.1 Where necessary, prepare access to the area
to be cleared.
10.2 Shrubs, bushes and trees are cleared using
excavators and bulldozers / other approved machineries.
10.3 All the cleared trees and shrubs are piled
and placed at convenient places.
10.4 The cleared trees and shrubs are then loaded
on to lorries and disposed at approved disposal site. Maintain records of
disposal records at relevant inspection checklist.
10.5 Submit Request for Inspection Form for joint
inspection and record joint measurement with client / client’s representative
in Surveying Record Book.
10.6 On completion of joint inspection, request
client / client’s representative to sign on the Request for Inspection Form and
file as per Project Filing Index.
10.7 Carry out computation and submit for claim.
11.0
TRAFFIC MANAGEMENT AND MONITORING
11.1 Maintenance of
Existing Roads, Footpaths and Service Drains, Etc.
The construction team
shall maintain all existing site excess, roads, footpath, service drain, etc.
and reinstate any damage caused by any reason whatsoever during the progress of
the works.
It will be the Safety
Officer/Supervisor’s responsibility to ensure that ingress and egress to the
site are kept free from obstruction brought about by the work on this site and
in no way shall cause hindrance to traffic or ancillary works either by his own
vehicles or by his work people, material, etc.
12.0
SAFETY PROGRAMME
12.1 Temporary Works and Public Safety
The Safety Officer/Supervisor shall be
responsible for submission of plans and drawings to the relevant Authorities
for the construction of all the necessary temporary drains and desilting pits,
safety nettings for the works.
The Safety Officer/Supervisor shall
provide adequate signboards at all strategic positions warning the public to
keep away from the work site and erect temporary fencing and barriers where
necessary around the site to prevent unauthorized trespassing during works.
13.0ENVIRONMENTAL PROGRAMME
All works should be carried out in
accordance to best practice environmental management as defined in the EMP for
the Construction Phase of the Muadzam Shah Cattle Research and Innovation
Centre.
13.1 Site Access.
The access as well as the portion of
public road and walkway connected with it shall be kept clean and safe at all
time.
13.2 Temporary
Work.
Existing drain shall be identified by
contractor together with the flow of drain until discharge point in order to
make use of it during clearing work. Silt trap shall be provided before any
discharge of surface water within site towards existing drain. This work should
be completed prior to the commencement of any site clearing activities.
Temporary earth drain shall be constructed
along clearing area to retain the surface water from dismissal directly towards
existing drain. Desilting work shall be carried out regularly and the existing
drain will be maintained during site clearing work.
As the slope area will not be disturbed,
the existing turf or grown grass shall be remain and only manually cut the
grown trees without uprooting it. Plastic sheet /canvas will be provided on
site on standby basis in order to be use as slope protection if necessary.
Any effluent discharges from the site must
comply with the Third Schedule of the Environmental Quality (Sewage and
Industrial Effulents) Regulation 1979.
13.3 Waste Management.
Any
construction wastes, solid wastes and domestic wastes other than schedule
wastes must be disposed off at the approved disposal site. On site compositing
for biodegradable waste is allowable but land filling and open burning
activities for the solid waste are strictly prohibited.
Good reference to prepare method statement. Very useful. Many thanks.
ReplyDeletevery useful
ReplyDeleteشركة النجوم مكافحة حشرات رش مبيدات نقل اثاث تسليك مجاري تنظيف
ReplyDeleteشركه تسليك مجاري بالطائف
شركة عزل خزانات بالطائف
شركة تسليك مجارى بمكة
thank you for the information .. it help my work environment
ReplyDeletegod bless.
How
ReplyDelete