1.0
OBJECTIVE
This Work Method
Statement is to outline the sequence of activities, method and resources needed
for the operation of repairing for structural element.
2.0
SCOPE OF WORKS
This method
statement shall be used for structural repair for (your project name). Details of the
procedures contained herein may be modified based upon actual ground condition
and site requirements.
3.0
REFERENCES
Ø Construction
Drawings
Ø Approved
Shop Drawings
Ø Project
Specifications
4.0
RESPONSIBILITIES
Ø Safety
Officer/Supervisor
Ø Site
Manager
Ø Project
Engineer
Ø Site
Supervisor
5.0
MATERIALS
Ø
Sika MonoTop – 610MY
Ø
Sika MonoTop – R
Ø
Sika Grout 215
Ø
Axel Mortar 302i
6.0
PLANT, MACHINERY AND EQUIPMENT
Mixer
machine, wheelbarrows, wire brush, angle grinder, measuring tapes, and other
handy tools.
7.0
HANDLING AND STORAGE OF MATERIALS
Handling - Transport of materials shall be
carried out by lorry or other suitable machinery.
Storage - Covered and raised above floor
level.
8.0
WORK METHODOLOGY
Method 1
– Re-cast Concrete Structure
i.
Identify and demarcate the member which needs
to be demolished.
ii.
Erect adequate temporary props to support the affected
slab and beam.
iii.
Demolish the severe concrete structure by
means of hacking with pneumatic tools. Ensure the edge of the concrete is
clean, sound and free from dirt or dust.
iv.
Care should be taken not to damage the
existing reinforcement.
v.
Bonding Preparation - Apply one coat of
bonding agent Sika Monotop – 610MY at the edge of existing concrete to receive
new concrete.
vi.
Formwork – Erect formworks at the demolished
area and secure the formwork with suitable ties.
vii.
Request for work inspection as per inspection
checklist for concreting.
viii.
Pour the concrete with waterproofing admixture
to the prepared formwork. Ensure the concrete has sufficient vibration during
concreting.
ix.
On completion carryout joint inspection to
sign on inspection checklist for post concrete.
Method 2
- Concrete Repair- Formwork Grouting
i.
Based on structural repair layout, mark on
existing structure such as concrete honeycomb.
ii.
Surface Preparation - Cut and hack around at
demarcated honeycomb area with suitable tool and equipment. Ensure all loose concrete must be removed
down to sound concrete. (Note: Do not use an impact hammer greater than 15
pound)
iii.
Clean existing reinforcement and clean/remove
debris or loose concrete fragments from the rectification area.
iv.
Request for work inspection as per inspection
checklist for concrete repair.
v.
Formwork –Install formworks that cover the
size of the repair area including place a layer of sponge at the perimeter with
suitable tied.
vi.
Install Inlet and Outlet - Drill two rows
(upper and lower part) of 25mmØ holes on the formwork to insert 25mmØ UPVC pipe
with spacing of 600mm c/c.
vii.
Mix the pre-bagged polymer modified shrinkage
compensated high strength grout – Sika Grout with adequate water in a mixing
drum. 6mm to 10mm aggregate shall be added and mixed with the grout at a ratio
of 1:1 by weight to minimize heat generation.
viii.
The Sika Grout 215 concrete grout is then
poured into the pump. Pump the grout into the form work with the lowers
injection port until the grout is going out from the upper port.
ix.
Curing - Leave the formwork in place for at
least 24 hours. Upon removal of the formwork, cure the exposed surfaces
immediately with water.
x.
On completion carryout joint inspection to
sign on inspection checklist for concrete repair.
Method 3
- Concrete Repair- Formwork Grouting for honeycomb depth > 20mm
i.
Based on structural repair layout, mark on
existing structure such as concrete honeycomb.
ii.
Surface Preparation - Cut and hack around at
demarcated honeycomb area with suitable tool and equipment. Ensure all loose concrete must be removed
down to sound concrete. (Note: Do not use an impact hammer greater than 15
pound)
iii.
Clean existing reinforcement and clean/remove
debris or loose concrete fragments from the rectification area.
iv.
Request for work inspection as per inspection
checklist for concrete repair.
v.
Formwork –Install formworks that cover the
size of the repair area including place a layer of sponge at the perimeter with
suitable tied.
vi.
Install Inlet and Outlet - Drill two rows
(upper and lower part) of 25mmØ holes on the formwork to insert 25mmØ UPVC pipe
with spacing of 600mm c/c.
vii.
Flowable Sika Grout 215 - Place about 4.0 to
4.4 litres clean water into clean container; add the whole bag of Sika Grout
215 (25kg) while continuously mixing. After mixing, stir lightly with a spatula
for few seconds to release any entrapped air.
viii.
The Sika Grout 215 concrete grout is then
poured into the pump. Pump the grout into the formwork with the lowers
injection port until the grout is going out from the upper port.
ix.
Curing - Leave the formwork in place for at
least 24 hours. Upon removal of the formwork, cure the exposed surfaces
immediately with water.
x.
On completion carryout joint inspection to
sign on inspection checklist for concrete repair.
Method 4
- Concrete Hand Patch Repair (for area < 0.5m2 at depth < 20mm)
i.
Based on structural layout, mark on existing
structure such as concrete honeycomb.
ii.
Cut around demarcated honeycomb area to
eliminate feather edge.
iii.
Surface Preparation - Repair area shall be
clean, sound and free from all loosely adhering particles.
iv.
Bonding Preparation - Apply one coat of
bonding agent Sika Monotop – 610MY “wet on wet” to the rectify area.
v.
Request for work inspection as per inspection
checklist for concrete repair.
vi.
Concrete Mixing - The cement mortar Sika
Monotop – R should be mixed in a clean drum. Place 3.4-3.5 litres of water into
the drum and add Sika Monotop - R slowly while mixing.
vii.
Application - Work wet on wet the mixed mortar
well into the rectify substrate, using a placing suitable tool, compact well.
Steel trowel the final coat if required.
viii.
On completion carryout joint inspection to
sign on inspection checklist for concrete repair.
Method 5
– Injection Grouting for Rectification of Spun Pile
i.
Based on piling layout, mark on the affected
pile.
ii.
Request for work inspection as per inspection
checklist for concrete repair.
iii.
Clean existing reinforcement and clean/remove
debris or loose concrete fragments from the rectification area.
iv.
Flowable Sika Grout 215 - Place about 4.0 to
4.4 litres clean water into clean container; add the whole bag of Sika Grout
215 (25kg) while continuously mixing. After mixing, stir lightly with a spatula
for few seconds to release any entrapped air.
v.
Insert the 75mm UPVC pipe into the pile hole.
vi.
The Sika Grout 215 concrete grout is then
poured into the pipe.
vii.
Curing – Cover the pile head for at least 24
hours. Upon removal of the cover, cure the exposed surfaces immediately with
water.
viii.
On completion carryout joint inspection to
sign on inspection checklist for concrete repair.
Method 6
– Pile Head Repair
i.
Based on piling layout, mark on the affected
pile.
ii.
Request for work inspection as per inspection
checklist for concrete repair.
iii.
Ensure that the
base is properly prepared, removed of all loose concrete debris, oil, dirt and
is then primed with Axel Primer S at 50 microns DFT for stubborn surface (if
any).
iv.
After the floor is
prepared, mix Axel Mortar 301i with Part A and B with a hopper or mixer drill
for 5 minutes until the mix is homogeneous. Trowel the mix over the prepared
floor with a metal trowel. Use Axel Solvent 914 to clean trowel before each
application for smooth finishing.
v.
After the pile has
been hacked or prepared, mix Axel Mortar 302i with a hopper, mixer drill or
hand mix (for small quantity) for 5 minutes and then mould the grout to a “moth
ball” and press it over the prepared surface. Use a glove and wet it with soap
water to even out the grout to a smooth finish.
vi.
Only use spatula
hand mixing for small quantity batching.
Method 7
– Broken/Damaged Pile Repair
i.
Based on piling layout, mark on the affected
pile.
ii.
Request for work inspection as per inspection
checklist for concrete repair.
iii.
Ensure that the base is properly prepared,
removed of all loose concrete debris, oil, dirt and is then primed with Axel
Primer S at 50 microns DFT for stubborn surface (if any).
iv.
After the floor is prepared, mix Axel Mortar
301i with Part A and B with a hopper or mixer drill for 5 minutes until the mix
is homogeneous. Trowel the mix over the prepared floor with a metal trowel. Use
Axel Solvent 914 to clean trowel before each application for smooth finishing.
v.
After the pile has been hacked or prepared,
mix Axel Mortar 302i with a hopper, mixer drill or hand mix (for small
quantity) for 5 minutes and then mould the grout to a “moth ball” and press it
over the prepared surface. Use a glove and wet it with soap water to even out
the grout to a smooth finish.
vi.
Only use spatula hand mixing for small
quantity batching.
9.0 HEALTH,
SAFETY & ENVIRONMENT PROGRAMME
9.1 Health
& Safety
Ø
Safety induction to be conducted to all new workers
that involved to this activity and safety toolbox meeting shall be conducted
every day to remind the workers about concerning the safety.
Ø
All workers shall be provided with PPE
(Personal Protective Equipment) and shall be always worn on site. Safety
Officer / Safety Supervisor shall ensure all the workers wear all the safety
equipment provided.
Ø
All workers shall be advised to report any
accident or injury to supervisor.
Ø
Proper and adequate provision of temporary
signage’s and barricades at diversion and temporary haul road as necessary (if
applicable).
Ø
Permit to work must be applied for night works
(if any).
9.2
Environment
Ø
All workers shall educate on good
environmental management practices and well-disciplined to environment.
Ø
The garbage bin shall be provided at the
working area and supervisor shall ensure its must be collected regularly and
disposed-off at the approved dumpsite.
Ø
All workers shall ensure that all tools and
equipment machinery are in good condition to avoid any oil leakage that could
harm to environment.