1.0
OBJECTIVE
To outline the method statement by which the
earthworks are carried out. This shall include method statement for excavation
and backfilling works.
2.0
SCOPE
The activities for earthwork shall consist of many
stages that include:
·
Preliminary work
·
Excavation
·
Excavation in rock (if any)
·
Embankment fill
·
Slope protection
3.0
REFERENCES
·
Construction
Drawings
·
Project
Specifications
·
Surveying Field
Book
4.0
DEFINITIONS
-Nil
5.0
RESPONSIBILITIES
·
Safety
Officer/Supervisor
·
Site Manager
·
Project
Engineer
·
Land Surveyor
·
Site Supervisor
6.0
MATERIALS
-Nil
7.0
HANDLING AND STORAGE OF MATERIALS
Handling : Transport of materials shall be
carried out by dump trucks / other suitable machinery.
Storage : Nil
8.0
PLANT, MACHINERY AND EQUIPMENT
Excavator : For bulk excavation and
slope trimming.
Dump
truck : For transporting
the material.
Bulldozer : For ripping, loosening of
earth, pushing and spreading the earth in layers for compaction.
Motor
grader : For spreading,
leveling and shaping works
Backhoe : For general excavation
in trenching works.
Water
bowser : For spraying of water.
Compactor
: For compacting soil
Back
pusher : For spreading and
leveling.
Survey
equipment : Theodolite / leveling.
9.0
PREPARATORY WORKS
Earthworks is based on the information and
data obtained in the following document:-
5
6
7
8
9
9.1
Earthworks
shall be carried out in accordance with standard code of practice (refer to BS
6031 : 2009) approved by consultant/consultant’s representative.
9.2
Approved Pre
Com plan endorsed by relevant Authority and Topographical Survey endorsed by
Licensed Surveyor.
9.3
Obtained
relevant approved construction drawing from consultant/consultant’s
representative.
9.4
Set out the
location, centre lines and limits of works.
9.5
Set out the toe
peg and finish level for the work.
9.6
Set temporary
earth drain and outlet structure before earthwork start.
9.7
Prepare temporary
shoring or any slope protection if required for work safety.
9.8
During
earthwork, temporary earth drain, sediment pond and outlet structure shall be
maintained regularly.
10.0
WORK METHODOLOGY
10.1 Preliminary Works
i.
Temporary
perimeter drain with silt trap and lorry wash trough shall be constructed as
per drawings.
ii.
Temporary drain
shall also be constructed from identified ponding areas to drain out the water
prior to any inspection and testing.
iii.
Joint
inspection shall be conducted with the Consultant Representative to identify
location of unsuitable /over wet materials and marked on a layout plan.
iv.
Suitable earth
shall be imported from cutting area to be identified by the Consultant
Representative.
v.
Survey to
establish existing ground level (EGL) and proposed formation level shall be in
accordance with contract, specification and drawings.
vi.
Surveyors shall
establish center line, boundary, slopes and level markers using wooden pegs
with appropriate tags or colour coded for easy reference. OGL survey drawing
shall be submitted before any actual earthwork to commence. OGL drawing shall
comply with the contract requirement.
vii.
All
encumbrances shall be cleared or isolated with proper boundary markers.
viii.
Inspection
shall be conducted to confirm PBM and proposed TBM.
10.2 Excavation
i.
The excavation
works shall proceed first at the location of cut areas detailed on the EGL
survey drawing to perform the waste and treatment pond.
ii.
Prior to any
cutting / excavation works, the surface of the ground shall be cleared of any
waste, rubbish material, organic material and etc using the excavator to scrap
the top surface.
iii.
Excavation
shall commence using excavators to form the required slope and formation level
which are control by the survey pegs. Excavation to be kept dry whether in open
cut or in trench.
iv.
The excavated
common material (not inclusive of rock) loaded into the dump truck and
transport to the designated filling area or temporary stockpile area approved
by Consultant Representative.
v.
Any unsuitable
materials identified as such shall be removed and transferred to other
designated area upon approval from the Consultant / PMC Representative.
vi.
Excavation
materials for embankment fill shall be tested and complied with the clause
2.4.1(e) of the Technical Specification.
10.3 Excavation
in Rock (If any)
i.
Normal hydraulic excavation method cannot be
employed for excavation of rock in trench or pit.
ii.
For this, the rock shall be loosened either by
drilling or blasting or by pneumatic tools. Normally pneumatic breaker or
explosives are used to disintegrate the rock formation depending on the type
and quantity of the rocks. The excavated rock shall be transport to the
Consultant Representative approved stockpile area.
iii.
A method statement shall be formulated and
submitted upon encountering new method of excavation in rock (if necessary).
10.4 Embankment Fill (if necessary)
i.
Suitable fill
materials shall be hauled by dumper trucks to the designated fill areas.
ii.
If suitable
fill materials cannot be spread immediately, it shall be deposited at temporary
stockpile area and then shall be shaped and compacted to ensure proper surface
drainage.
iii.
The fill
material shall be deposited, spread, levelled and compacted using vibro
compactor exceeding 20tonne. The maximum loose thickness for fill is 500mm each
layer. For compaction of embankment slope, the fill shall be extended 600mm
beyond the design slope and then trim back to the required slope angle. Degree
of compaction for the whole embankment below the top 300mm of the subgrade
shall not less than 90% of the Maximum Dry Density (MDD).
iv.
When compaction
has reached the full berm height, motor grader shall be used to grade the
surface to the line, grade and level for the next construction activities.
v.
The fill layer
shall be built up evenly over the full width or up to the roadworks limit only
(to facilitate the subsoil drain construction) with sufficient width (to ensure
adequate compaction) and shall be always maintained with sufficient camber to
avoid water ponding.
vi.
In-situ Field
Density Testing and CBR test shall be carried out on the subgrade and
subsequent layers at the rate specified in contract or as deemed necessary at
location to be selected by the Consultant Representative.
Subject
to FDT result approval, compaction of the layers shall be continued as the
following :-
·
If FDT passed –
proceed next layer
·
If FDT failed –
proceed with rectification and retesting
vii.
Upon
confirmation of the Consultant Representative, the subsequent layer shall be
carried out as per sequence until formation level is reached.
viii.
Each inspection
sheet shall be signed off every day by contractor and the Consultant
Representative.
10.5 Slope
Protection
i.
A gentle
gradient shall be adopted to have a more stable slope.
ii.
Where the
condition of high gradient (i.e. steep slope), turfing of the area shall be
applied or staggering of slope shall be done (if applicable) to prevent any
erosion due to weather or other means.
10.6 Inspection
and Test Plan
As the progress of the preparation for the
earthwork, there are few inspections involve for conformation and assurance of
the specified requirements.
The inspections required are:
i.
Field Density Test
Ø
Core Cutter Method
Ø
Sand Replacement Method – small cone
Ø
Sand Replacement Method – large cone
ii.
Soil Compaction Test with Soil Classification Test (Proctor)
iii.
California Bearing Test
Ø
Lab CBR Test (soaked)
Ø
In-situ CBR Test using Core Cutter method (soaked)
Ø
In-situ CBR Test using Load to carry out at site.
iv.
Grading Test (Sieve for Analysis)
v.
Mackintosh Probe Test
The testing equipment and laboratory apparatus
required are as below:
·
A balance accurate to 0.01g
·
A balance accurate to 0.5g
·
Air-tight non corrodible metal container (50mm OD x 25mm high)
·
Desiccators
·
Scoops
·
British Standard sieves as follows :
75mm, 63mm, 50mm, 37.5mm, 28mm, 20mm, 14mm, 6.3mm,
5mm, 3.35mm, 2mm, 1.18mm, 425mm, 212mm, 150mm and 63mm and appropriate
receivers.
·
Cone penetrator or Casagrande liquid apparatus
·
Other suitable accessories and equipment necessary to carry out density
test (including In-situ Test) sieve analysis, liquid limit analysis, CBR,
Mackintosh probe and etc.
11.0
TRAFFIC MANAGEMENT AND MONITORING
11.1 Maintenance of existing
roads, footpaths and service drains, etc.
The construction team shall maintain all
existing site excess, roads, footpath, service drain, etc. and reinstate any
damage caused by any reason whatsoever during the progress of the works.
It will be the Safety Officer/Supervisor’s
responsibility to ensure that ingress and egress to the site are kept free from
obstruction brought about by the work on this site and in no way shall cause
hindrance to traffic or ancillary works either by his own vehicles or by his
work people, material, etc.
12.0
SAFETY PROGRAMME
12.1 Temporary Works and Public Safety
The Safety Officer/Supervisor shall be
responsible for submission of plans and drawings to the relevant Authorities
for the construction of all the necessary temporary drains and desilting pits,
safety nettings for the works.
The Safety Officer/Supervisor shall provide
adequate signboards at all strategic positions warning the public to keep away
from the work site and erect temporary fencing and barriers where necessary
around the site to prevent unauthorized trespassing during works.
13.0 ENVIRONMENTAL
PROGRAMME
All works should be carried out in
accordance to best practice environmental management as defined in the EMP.
13.1 Site Access.
The access as well as the portion of public
road and walkway connected with it shall be kept clean and safe at all times.
13.2 Temporary
Work.
Existing drain shall be identified by
contractor together with the flow of drain until discharge point in order to
make use of it during clearing work. Silt trap shall be provided before any
discharge of surface water within site towards existing drain. This work should
be completed prior to the commencement of any site clearing activities.
Temporary earth drain shall be constructed
along clearing area to retain the surface water from dismissal directly towards
existing drain. Desilting work shall be carried out regularly and the existing
drain will be maintained during site clearing work.
As the slope area will not be disturbed, the
existing turf or grown grass shall be remain and only manually cut the grown
trees without uprooting it. Plastic sheet /canvas will be provided on site on
standby basis in order to be use as slope protection if necessary.
Any effluent discharges from the site must
comply with the Third Schedule of the Environmental Quality (Sewage and
Industrial Effluents) Regulation 1979.
13.3 Waste Management.
Any construction wastes, solid wastes and
domestic wastes other than schedule wastes must be disposed-off at the approved
disposal site. On site compositing for biodegradable waste is allowable but
land filling and open burning activities for the solid waste are strictly
prohibited.