1.0 OBJECTIVE
This Work Method
Statement is to outline the sequence of activities, method and resources needed
for the operation of rubble pitching’s construction.
2.0 SCOPE
This method
statement shall be used for failure slope protection, abutment and river
protection for the (your project name). Details of the procedures contained herein
may be modified based upon actual ground condition and site requirements.
3.0 REFERENCES
Ø Construction
Drawings
Ø Approved
Shop Drawings
Ø Project
Specifications
4.0 RESPONSIBILITIES
Ø Site
Manager
Ø Project
Engineer
Ø Site
Supervisor
5.0 MATERIALS
Ø
Stone
Ø
75mm Dia. UPVC Pipe
Ø
Geotextile
Ø
Graded Granular
Ø
Ordinary Portland Cement
Ø
Fine Aggregate
6.0 HANDLING AND STORAGE OF MATERIALS
Handling - Transport of materials shall be
carried out by lorry or other suitable machinery.
Storage - Covered and raised above floor
level.
7.0 PLANT, MACHINERY AND EQUIPMENT
Ø
Concrete Mixer
Ø
Hand Tools
8.0 PREPARATORY WORKS
i.
Obtained relevant approved construction drawing from
consultant/consultant’s representative.
ii.
Set out the location, center lines and limits of work.
iii.
Set out the toe peg and finish level for the work.
iv.
Set temporary earth drain and outlet structure before work starts (if
required).
9.0 WORK METHODOLOGY
i.
Moisten the work surface with clean water a little in advance of
construction.
ii.
Lay the cement mortar about 50mm thickness.
iii.
Construction of rubble pitching shall commence at the lowest part of
each structure or section of a structure and continue progressively upward.
iv.
The pitching
shall be laid in horizontal courses with headers at intervals or in random
fashion depending on the stone available.
v.
Place the stones
firmly set by hand into the mortar, densely packed against adjacent stones and
built up to form a stone structure of uniform thickness as shown in the
drawing.
vi.
For abutment
and river protection at bridge area, one layer of geotextile type A will be
laid as per drawing.
vii.
To fill the mortar with hand-placed space between the stones from bottom
to top.
viii.
Clean the surface to expose the individual stone faces.
ix.
To provide the weep holes as shown in the drawing.
x.
To finish the pitching
with a horizontal course at the level shown on the drawing.
10.0 TRAFFIC MANAGEMENT AND MONITORING
10.1 Maintenance of existing roads, footpaths and service drains, etc.
The construction team shall maintain all existing site excess, roads, footpath, service drain, etc. and reinstate any damage caused by any reason whatsoever during the progress of the works.
It will be the Safety Officer/Supervisor’s
responsibility to ensure that ingress and egress to the site are kept free from
obstruction brought about by the work on this site and in no way shall cause
hindrance to traffic or ancillary works either by his own vehicles or by his
work people, material, etc.
11.0 SAFETY PROGRAMME
11.1 Temporary Works and Public Safety
The Safety Officer/Supervisor shall be responsible for submission of plans and drawings to the relevant Authorities for the construction of all the necessary temporary drains and desilting pits, safety nettings for the works.
The
Safety Officer/Supervisor shall provide adequate signboards at all strategic
positions warning the public to keep away from the work site and erect
temporary fencing and barriers where necessary around the site to prevent
unauthorized trespassing during works.
12.0 ENVIRONMENTAL PROGRAMME
All works should be carried out in accordance with best practice environmental management as defined in the EMP.
12.1 Site Access.
The access as well as the portion of public road and walkway connected with it shall be kept clean and safe at all times.
12.2 Temporary Work.
Existing drain shall be identified by contractor together with the flow of drain until discharge point in order to make use of it during repairing work. Silt trap shall be provided before any discharge of surface water within site towards existing drain. This work should be completed prior to the commencement of any activities.
Temporary earth drain shall be constructed along clearing area to retain the surface water from dismissal directly towards existing drain. Desilting work shall be carried out regularly and the existing drain will be maintained during work.
As the slope area will not be disturbed, the existing turf or grown grass shall be remain and only manually cut the grown trees without uprooting it. Plastic sheet /canvas will be provided on site on standby basis in order to be use as slope protection if necessary.
Any effluent discharges from the site must comply with the Third Schedule of the Environmental Quality (Sewage and Industrial Effluents) Regulation 1979.
12.3 Waste Management.
Any construction wastes, solid wastes and
domestic wastes other than schedule wastes must be disposed-off at the approved
disposal site. On site compositing for biodegradable waste is allowable but
land filling and open burning activities for the solid waste are strictly
prohibited.