Method Statement -Honeycomb Concrete Repair

1.0    OBJECTIVE
     
Outline the Method statement for Concrete Repair - Honey Comb for structural element.

2.0    SCOPE OF WORK

This method statement shall be used for structural repair for structural elements.

3.0    RESPONSIBILITY

Site Supervisor, Project Engineer

4.0    MATERIALS
   
·         Sika MonoTop – 610MY
·         Sika MonoTop – R
·         Sika Grout 215

5.0    HANDLING AND STORAGE OF MATERIALS

Handling - Transport of materials shall be carried out by lorry or other suitable machinery.

Storage – Covered and raised above floor level.

6.0    PLANT, MACHINERY AND EQUIPMENT

Mixer machine, wheelbarrows, wire brush, angle grinder, measuring tapes, and other handy tools.

7.0    PREPARATORY WORKS

Obtain approved structural repair layout and details from the client / client’s representative.
Submit inspection checklist for concrete repair to client / client’s representative when carry out concrete repair works.



8.0    WORK METHODOLOGY

Method 1 – Re-cast Concrete Structure

i            Identify and demarcate the member which need to be demolished.
ii           Erect adequate temporary props to support the affected slab and beam.
iii          Demolish the severe concrete structure by means hacking with pneumatic tools. Ensure the edge of the concrete is clean, sound and free from dirt or dust.
iv          Care should be taken not to damage the existing reinforcement of the beam and slab.
v           Bonding Preparation - Apply one coat of bonding agent Sika Monotop – 610MY at the edge of existing concrete to receive new concrete.
vi          Formwork – Erect formworks at the demolished area and secure the formwork with suitable ties.
vii         Request for inspection as per inspection checklist for concreting
viii        Pour ready-mixed concrete Grade 40 with waterproofing admixture to the prepared formwork. Ensure the concrete have sufficient vibration during concreting.
ix          On completion carryout joint inspection to sign on inspection checklist for post concrete.

Method 2 - Concrete Repair- Formwork Grouting

i.                Based on structural repair layout, mark on existing structure such as concrete honeycomb.
ii           Surface Preparation - Cut and hack around at demarcated honeycomb area with suitable tool and equipment.  Ensure all loose concrete must be removed down to sound concrete. (Note: Do not use an impact hammer greater than 15 pound)
iii          Clean existing reinforcement and clean/remove debris or loose concrete fragment from the rectification area.
iv          Request for inspection as per inspection checklist for concrete repair.
v           Formwork –Install formworks that cover the size of the repair area including place a layer of sponge at the perimeter with suitable tied.
vi          Install Inlet And Outlet - Drill two rows (upper and lower part) of 25mmØ holes on the formwork to insert 25mmØ UPVC pipe with spacing of 600mm c/c.
vii         Mix the pre-bagged polymer modified shrinkage compensated high strength grout – Sika Grout with adequate water in a mixing drum. 6mm to 10mm aggregate shall be added and mixed with the grout at a ratio of 1:1 by weight to minimize heat generation.
viii        The Sika Grout 215 concrete grout is then poured into the pump. Pump the grout into the form work with the lowers injection port until the grout is going out from the upper port.
ix          Curing - Leave the formwork in place for at least 24 hour. Upon removal of the formwork, cure the exposed surfaces immediately with water.
x           On completion carryout joint inspection to sign on inspection checklist for concrete repair.

Method 3 - Concrete Repair- Formwork Grouting for honeycomb depth > 20mm

i            Based on structural repair layout, mark on existing structure such as concrete honeycomb.
ii           Surface Preparation - Cut and hack around at demarcated honeycomb area with suitable tool and equipment.  Ensure all loose concrete must be removed down to sound concrete. (Note: Do not use an impact hammer greater than 15 pound)
iii          Clean existing reinforcement  and clean/remove debris or loose concrete fragment from the rectification area.
iv          Request for inspection as per inspection checklist for concrete repair.
v           Formwork –Install formworks that cover the size of the repair area including place a layer of sponge at the perimeter with suitable tied.
vi          Install Inlet And Outlet - Drill two rows (upper and lower part) of 25mmØ holes on the formwork to insert 25mmØ UPVC pipe with spacing of 600mm c/c.
vii         Flowable Sika Grout 215 - Place about 4.0 to 4.4 litres clean water into clean container; add the whole bag of Sika Grout 215 (25kg) while continuously mixing. After mixing, stir lightly with a spatula for few seconds to release any entrapped air.
viii        The Sika Grout 215 concrete grout is then poured into the pump. Pump the grout into the form work with the lowers injection port until the grout is going out from the upper port.
ix          Curing - Leave the formwork in place for at least 24 hour. Upon removal of the formwork, cure the exposed surfaces immediately with water.
x           On completion carryout joint inspection to sign on inspection checklist for concrete repair.

Method 4 - Concrete Hand Patch Repair (for area < 0.5m2 at depth < 20mm)

i            Based on structural layout, mark on existing structure such as concrete honeycomb.
ii           Cut around demarcated honeycomb area to eliminate feather edge.
iii          Surface Preparation - Repair area shall be clean, sound and free from all loosely adhering particles.
iv          Bonding Preparation - Apply one coat of bonding agent Sika Monotop – 610MY “wet on wet” to the rectify area.
v           Request for inspection as per inspection checklist for concrete repair.
vi          Concrete Mixing - The cement mortar Sika Monotop – R should be mixed in a clean drum. Place 3.4-3.5 litres of water in to the drum and add Sika Monotop - R slowly while mixing.
vii         Application - Work wet on wet the mixed mortar well into the rectify substrate, using a placing suitable tools, compact well. Steel trowel the final coat if required.
viii        On completion carryout joint inspection to sign on inspection checklist for concrete repair.

9.0 SAFETY & ENVIRONMENTAL PROGRAMME

·         All HSSE procedure and regulations shall be complied with.
·         To provide proper and safe access for inspection and working.
·         Site personnel must be in proper safety working attire e.g. Safety boots and helmets must be worn at all times.
·         Proper and adequate lighting to be provided when working at night.
·         Water ponding must be constantly pumped out and mosquito infestation checked and controlled.


10.0 QA/QC PROGRAMME

10.1       Inspections and Test Plan
In order to ensure the quality of honeycomb concrete repair works meet the requirement, inspection and test shall be carried out as per the Project Quality Plan (PQP).



•             Inspection Request Form (IRF) attached with Checklist

10 comments:

  1. We Specialize in Aluminium Honeycomb Cores and Aluminium Honeycomb Panels. Our custom laminating and extensive material knowledge helps to provide our customers with infinite composite panel possibilities.
    http://www.alu-honeycomb-material.com/c/laser-cutting-platform-panel_0014

    ReplyDelete
  2. All the contents you mentioned in post is too good and can be very useful. I will keep it in mind, thanks for sharing the information keep updating, looking forward for more posts.Thanks Nanaimo Drainage

    ReplyDelete
  3. Really a amazing info.. Thanks for posting.
    Whether you require repairs for your potholes or advice on achieving better drainage on your driveway, our staff can help improve the safety and value of your property.
    Construction Companies Winnipeg
    Concrete Paver Winnipeg

    ReplyDelete
  4. Its a great pleasure reading your post.Its full of information I am looking for and I love to post a comment that "The content of your post is awesome" Great work. concret York PA

    ReplyDelete